Telecom Takeoff
[!info] Scope
- Telephone
- Data
- Cable TV
Important
Not to be confused with low-voltage-takeoff.
Note: Empty Conduit
Where COMMON ASSEMBLIES/PDI EMPTY & DUCTBANK CONDUIT/...
is specified, FEEDER CONDUIT AND WIRE/...
is also acceptable.
Site Low Voltage Duct Bank
-
Area= "2 - Site"Phase= "Site"System= "LVD - Site Low Voltage Ductbank"Bid Item= "1 - Site"
COMMON ASSEMBLIES/PDI EMPTY & DUCTBANK CONDUIT/...- Size and quantity per proposal > drawings > assume (4) 4"C
- Length = Length measured from MDF to 5ft beyond building footprint
Garden Style: Outside of every building
[!important] Long-Radius Elbows Note requirements for long-radius elbows, substitute items as necessary.
Telecom Vaults
"Quazite Box" polymer concrete enclosure
TEMPORARY ITEMS/Quazite Box ...- Material Price = 1000.00
- Labor Hours = 12.00
- Sort Code ? = 200
Alternative
COMMON ASSEMBLIES/POLES / EXCAVATION / CORING / UG PULL BX/MANHOLES / PULL BOXES / EXCAVATION / CONCRETE/QUAZITE UG PULL BOXES/...
Backbone Riser
Phase= "Building - BOH ..."System= "TC - Telecom Backbone"
If not shown:
- Garden Style: (2) 4"C
- High Rise, Mid Rise: (4) 4"C
Horizontal Backbone
-
Drawing= Telecom riser diagramArea= Area of riser room
COMMON ASSEMBLIES/PDI EMPTY & DUCTBANK CONDUIT/...- Length = Length measured from MDF to IDF
- Input adder length to reach the level of the IDF (Minimum 15ft).
Vertical Backbone
-
Drawing= Telecom riser diagramArea= "Typical - Building All Levels"
COMMON ASSEMBLIES/PDI EMPTY & DUCTBANK CONDUIT/...- Delete elbows if unnecessary.
- Length = Height between floors (Minimum 15ft)
Telecom Backboards
As shown on plans, only if not excluded in proposal.
-
Phase= "Building - BOH ..."System= "TC - Telecom Backbone"
COMMON ASSEMBLIES/MISC ASSEMBLIES/... PLYWOOD BACKBOARD- Count = As shown
Corridor Conduit (IDF to Unit MSDE)
One Takeoff per Area per level
COMMON ASSEMBLIES/PDI EMPTY & DUCTBANK CONDUIT/...- Length = Average of subfeed lengths * # of Units
- Count = # of Units
Inner Duct
For future use (e.g. fiber)
TEMPORARY ITEMS/MaxCell 3" 3 Cell- Material Price = 450.00/C
- Labor Hours = 12.00/C
Alternative:
COMMON ASSEMBLIES/TELECOM SYSTEMS/INNERDUCT/... (GP)
Devices
As shown on plans. Ignore scope shared with electrical-takeoff (e.g. floor boxes).
COMMON ASSEMBLIES/TELECOM SYSTEMS/...- .../
BOH / AMENITY ASSEMBLIES - .../
SCREWLESS DECORA COVERS UNITS / BOH - .../
ROUGH IN ASSY
- .../
If system is included, take off both rough-in and device assemblies in amenity areas.
If rough-in is included, always provide backboxes and conduit stub-ups for outlets in other than units, even if qualified as "free-air per code" or similar.1