title: Three-Point Estimation
|
||||
tags: []
|
||||
---
|
||||
# Three-Point Estimation
|
||||
|
||||
* best-case or optimistic
|
||||
* worst-case or pessimistic
|
||||
* most-likely
|
||||
|
||||
[Wikipedia](https://en.wikipedia.org/wiki/Three-point_estimation)
|
||||
|
||||
[PMI](https://www.projectmanagement.com/wikis/368763/3-points-estimating)
|
||||
|
||||

|
||||
|
||||
A [[risk]]-neutral party would set selling price at the most likely.
|
||||
The difference between the pessimistic estimate and selling price
|
||||
is the [[value-at-risk]].
|
||||
|
||||
Three-point estimating is considered the bare minimum in most industries.
|
||||
@@ -14,8 +14,8 @@ but I think often of [[construction-estimating|estimators]]
|
||||
like I once knew well,
|
||||
who somehow managed to be in the industry for decades
|
||||
while believing that it is poor estimating
|
||||
to accept any risk in a bid,
|
||||
that all uncertainty must be clarified.
|
||||
to accept any [[risk]] in a bid,
|
||||
that all [[uncertainty]] must be clarified.
|
||||
|
||||
Of course,
|
||||
they didn't believe that with their actions,
|
||||
@@ -25,4 +25,34 @@ like you do when you're a new estimator
|
||||
who barely knows what the word means,
|
||||
you're just happy to be out of the field
|
||||
where it's hot and no one is ever happy.
|
||||
But you've got a brain between your ears,
|
||||
so you ask the estimator---
|
||||
we'll call him Steve---
|
||||
you ask Steve what the limit is,
|
||||
because obviously some scope
|
||||
Steve cranes his neck and squints at you, mouth half open.
|
||||
This is how he expresses incredulity.
|
||||
With that invitation, you continue:
|
||||
|
||||
Your time costs your owners about fifty dollars an hour
|
||||
including salary and burden,
|
||||
and Steve's time is worth even more.
|
||||
Between the time spent
|
||||
* quadruple checking that the question isn't answered in the documents,
|
||||
* considering whether you should wait until you have more questions,
|
||||
* typing the RFI and sending the email,
|
||||
* parsing the engineer's inevitably unhelpful response,
|
||||
* consulting with Steve for his interpretation,
|
||||
* and so on and so on,
|
||||
it's a safe bet that the average cost
|
||||
to officially resolve uncertainty of any magnitude
|
||||
is in the hundreds of dollars.
|
||||
|
||||
Assuming a contract win rate of fifty percent,
|
||||
any cost of [[risk-mitigation]]
|
||||
greater than half the reduction in [[value-at-risk]]
|
||||
represents a loss.
|
||||
|
||||
Steve moves the goalposts,
|
||||
says of course he didn't mean "the small stuff",
|
||||
and also that you're overcomplicating it.
|
||||
|
||||