## Pre-Takeoff Email Template Meeting
|
||||
|
||||
### Scratch
|
||||
|
||||
Meeting lead by Josh Ford
|
||||
to discuss acceptable use of [[conest-pre-takeoff-email-template]]
|
||||
to discuss acceptable use of [[conest-pre-takeoff-email-template]].
|
||||
|
||||
***
|
||||
### Topics
|
||||
|
||||
#### Purpose
|
||||
|
||||
Reiterated intent to replace OneNote,
|
||||
however stated that OneNote might (even should)
|
||||
be used to track
|
||||
|
||||
Template should be pasted into the email body,
|
||||
not sent as attachment.
|
||||
To be revisited in audit meeting [[2026-W13|next week]].
|
||||
|
||||
Intent is too provide information to the bid team
|
||||
potentially to be qualified in future bids.
|
||||
|
||||
***
|
||||
|
||||
> [!example] [[sunset-amphitheater]]
|
||||
> Cummins generator was spec'd, quoted,
|
||||
> but not used in estimate because it was not cheapest.
|
||||
|
||||
Josh, Corwin, Procurement
|
||||
to provide a list of "typical PDI manufactures"
|
||||
for Wire, Generator, Switchgear
|
||||
rather than include entire list from specs.
|
||||
|
||||
> Wire:
|
||||
> * Encore
|
||||
> * Okonite
|
||||
> * Southwire
|
||||
|
||||
***
|
||||
|
||||
[[conest-pre-takeoff-email-template#Project Drawing/Detail Callouts]]
|
||||
|
||||
High-cost impact items
|
||||
not mentioned in proposal
|
||||
not shown in Bid Sheet.
|
||||
|
||||
* dimming in units
|
||||
* balcony pedestals
|
||||
|
||||
***
|
||||
|
||||
[[conest-pre-takeoff-email-template#Lighting Control]]
|
||||
|
||||
Intent is to provoke conversation ahead of takeoff
|
||||
to prevent rework
|
||||
|
||||
not necessary to list all areas
|
||||
if not applicable to project
|
||||
(code minimum)
|
||||
|
||||
***
|
||||
|
||||
[[conest-pre-takeoff-email-template#Tasks/Quotes Needed for WBS]]
|
||||
|
||||
> BPM has both
|
||||
> tasks within bid round and
|
||||
> tasks outside of bid round.
|
||||
|
||||
to be revisited in dedicated meeting
|
||||
|
||||
***
|
||||
|
||||
cc: Josh Ford, Corwin Fluitt, Jessalyn
|
||||
|
||||
***
|
||||
|
||||
Response from Bid is necessary within three days.
|
||||
|
||||
"See proposal" is unacceptable response.
|
||||
Escalate issue.
|
||||
|
||||
***
|
||||
|
||||
> 1. ConEst deviates from specs based on direction from Bid.
|
||||
> 2. Awarded contract does not include respect for the direction
|
||||
> 3. Ops, not aware of direction, believes ConEst takeoff was in error.
|
||||
@@ -109,22 +44,6 @@ an area the OneNote is poor in.
|
||||
|
||||
***
|
||||
|
||||
Only when we're touching a job for the first time,
|
||||
not revisions.
|
||||
|
||||
***
|
||||
|
||||
Other media were considered,
|
||||
but email text was determined to be optimal
|
||||
to prevent lost attachments and broken links.
|
||||
|
||||
***
|
||||
|
||||
Consistency in formatting is prioritized
|
||||
ConEst resources to be allocated by availability, not region.
|
||||
|
||||
***
|
||||
|
||||
Direction from Aaron to improve turnaround
|
||||
while maintaining standards
|
||||
including presentability of information;
|
||||
@@ -158,8 +77,79 @@ but ConEst's role is to prevent PDI _from making bad deals_
|
||||
> Similar could be said by Ops about ConEst.
|
||||
> ~~They have more time than us~~
|
||||
|
||||
#### Use
|
||||
|
||||
Only when we're touching a job for the first time,
|
||||
not revisions.
|
||||
|
||||
Template should be pasted into the email body,
|
||||
not sent as attachment.
|
||||
To be revisited in audit meeting [[2026-W13|next week]].
|
||||
|
||||
cc: Josh Ford, Corwin Fluitt, Jessalyn
|
||||
|
||||
Other media were considered,
|
||||
but email text was determined to be optimal
|
||||
to prevent lost attachments and broken links.
|
||||
|
||||
Consistency in formatting is prioritized
|
||||
ConEst resources to be allocated by availability, not region.
|
||||
|
||||
Response from Bid is necessary within three days.
|
||||
|
||||
"See proposal" is unacceptable response.
|
||||
Escalate issue.
|
||||
|
||||
#### Acceptable Manufacturers
|
||||
|
||||
> [!example] [[sunset-amphitheater]]
|
||||
> Cummins generator was spec'd, quoted,
|
||||
> but not used in estimate because it was not cheapest.
|
||||
|
||||
Josh, Corwin, Procurement
|
||||
to provide a list of "typical PDI manufactures"
|
||||
for Wire, Generator, Switchgear
|
||||
rather than include entire list from specs.
|
||||
|
||||
> Wire:
|
||||
> * Encore
|
||||
> * Okonite
|
||||
> * Southwire
|
||||
|
||||
#### Project Drawing/Detail Callouts
|
||||
|
||||
[[conest-pre-takeoff-email-template#Project Drawing/Detail Callouts]]
|
||||
|
||||
High-cost impact items
|
||||
not mentioned in proposal
|
||||
not shown in Bid Sheet.
|
||||
|
||||
* dimming in units
|
||||
* balcony pedestals
|
||||
|
||||
#### Lighting Control
|
||||
|
||||
[[conest-pre-takeoff-email-template#Lighting Control]]
|
||||
|
||||
Intent is to provoke conversation ahead of takeoff
|
||||
to prevent rework
|
||||
|
||||
not necessary to list all areas
|
||||
if not applicable to project
|
||||
(code minimum)
|
||||
|
||||
#### Tasks/Quotes Needed for WBS
|
||||
|
||||
[[conest-pre-takeoff-email-template#Tasks/Quotes Needed for WBS]]
|
||||
|
||||
> BPM has both
|
||||
> tasks within bid round and
|
||||
> tasks outside of bid round.
|
||||
|
||||
To be revisited in [[[[2026-03-25_13-17-35#BPM Tasks Meeting|dedicated meeting]]
|
||||
|
||||
### Meetings to Follow
|
||||
|
||||
* ConEst Audit Scorecard --- [[2026-03-25]]
|
||||
* BPM --- TBD
|
||||
* BPM Tasks Meeting --- TBD
|
||||
* ConEst Town Hall --- TBD
|
||||
|
||||
@@ -18,6 +18,8 @@ yearly: "[[2026]]"
|
||||
---
|
||||
# 2026-03-20 13:44:59
|
||||
|
||||
## Unit Smoke Detectors
|
||||
|
||||
Relevant to [[fire-alarm-takeoff]],
|
||||
while reviewing my takeoff for [[1990-k-street]]
|
||||
Joel had to fix the assemblies I used for unit smoke detectors.
|
||||
|
||||
@@ -0,0 +1,77 @@
|
||||
---
|
||||
id: 2026-03-26T08:49:49-04:00
|
||||
aliases: []
|
||||
title: 2026-03-26 08:49:49
|
||||
tags:
|
||||
- authorship/original
|
||||
- destiny/permanent
|
||||
- status/draft
|
||||
- type/periodic/timestamped
|
||||
daily: "[[2026-03-26]]"
|
||||
date-created: 2026-03-26T08:49:49-04:00
|
||||
dg-publish: true
|
||||
monthly: "[[2026-03]]"
|
||||
quarterly: "[[2026-Q1]]"
|
||||
weekly: "[[2026-W13]]"
|
||||
yearly: "[[2026]]"
|
||||
---
|
||||
# 2026-03-26 08:49:49
|
||||
|
||||
## 1990 K Street Senior Review
|
||||
|
||||
Follow-up to [[2026-03-20_13-44-59#2026-03-20 13:44:59]].
|
||||
|
||||
Comments by Joel Jansen
|
||||
Relevant to my takeoff for [[1990-k-street]]:
|
||||
|
||||
### Lighting Control Assemblies
|
||||
|
||||
Relevant to [[lighting-controls-takeoff]]:
|
||||
|
||||
Lighting control assembly selection for the project was contentious
|
||||
because PDS excluded the system due to lack of information,
|
||||
but the drawings painted as exact a picture as one could ask for prior to construction.
|
||||
|
||||
> Design shows digital control, dimming controlled by occ sensors in stairwells, corridors. \
|
||||
> ---E021 AUTOMATED LIGHTING CONTROL - SEQUENCES OF OPERATIONS
|
||||
>
|
||||
> Proposal excludes digital lighting control due to lack of information. \
|
||||
> ---Proposal 2026-01-22, Pricing Alternates
|
||||
>
|
||||
> Spec 260923 - LIGHTING CONTROL DEVICES \
|
||||
> Spec 260936 - MODULAR DIMMING CONTROLS
|
||||
|
||||
In conversation with Joel,
|
||||
we agreed that I would use the "FBO" assemblies
|
||||
with the assumption that an LV system would be budgeted.
|
||||
|
||||
> [!quote] 1990 K Street ConEst OneNote, "Lighting Control"
|
||||
> Takeoff to use FBO assemblies (rough-in, cable, and device labor). \
|
||||
> ---Joel Jansen 2026-02-11 11:05
|
||||
|
||||
After direction I'm not clear on,
|
||||
Joel switched these to the device labor and material assemblies.
|
||||
|
||||
[[lighting-controls-research]]
|
||||
|
||||
### Feeder Schedule 5"C
|
||||
|
||||
Relevant to [[feeders-takeoff]]:
|
||||
|
||||
Feeder schedule calls for 5 inch conduit for certain tags
|
||||
which PDI's schedule uses 4 inch for.
|
||||
I did not respect this in the takeoff,
|
||||
Joel intends to substitute.
|
||||
|
||||
***
|
||||
|
||||
**\[2026-03-26 09:36\]**
|
||||
After conversation with Christian,
|
||||
Joel substituted all EMT feeders for MC cable.
|
||||
Christian stated that [[pdi-estimating#Bid Estimating|they]]
|
||||
would qualify the substitution in their next proposal
|
||||
and raised that 5 inch EMT does not exist in our database anyway[^1].
|
||||
|
||||
[^1]: It doesn't exist at all.
|
||||
See [[nfpa-70_358_emt#358.20(B) Maximum.|NEC 358.20(B)]].
|
||||
|
||||
@@ -0,0 +1,105 @@
|
||||
---
|
||||
id: 2026-03-26T14:10:46-04:00
|
||||
aliases: []
|
||||
title: 2026-03-26 14:10:46
|
||||
tags:
|
||||
- authorship/original
|
||||
- destiny/permanent
|
||||
- status/draft
|
||||
- type/periodic/timestamped
|
||||
- occupational
|
||||
dg-publish: true
|
||||
date-created: 2026-03-26T14:10:46-04:00
|
||||
daily: "[[2026-03-26]]"
|
||||
weekly: "[[2026-W13]]"
|
||||
monthly: "[[2026-03]]"
|
||||
quarterly: "[[2026-Q1]]"
|
||||
yearly: "[[2026]]"
|
||||
---
|
||||
# 2026-03-26 14:10:46
|
||||
|
||||
## 1990 K Street ConEst Manager Review
|
||||
|
||||
ConEst Manager Review for [[1990-k-street]]
|
||||
lead by Josh Ford and Joel Jansen
|
||||
|
||||
### Purpose of ConEst Manager Review
|
||||
|
||||
Josh explains purpose of this review to PE
|
||||
|
||||
Jobs below 12% margin
|
||||
are reviewed further with Corwin Fluitt
|
||||
who is able and authorized
|
||||
to "make judgement calls" on pricing concerns
|
||||
in order to get GP to an acceptable number.
|
||||
|
||||
PDI MC Cable pricing is market rate,
|
||||
we have vendor specific pricing with Southwire
|
||||
up to 20% lower
|
||||
|
||||
### Switchgear
|
||||
|
||||
Josh will usually not review switchgear takeoff
|
||||
unless there is significant difference from labor plan
|
||||
|
||||
### Primaries & Secondaries
|
||||
|
||||
Where PEPCO is the power utility:
|
||||
typically own nothing for primaries
|
||||
conduit only for secondaries.
|
||||
|
||||
Confirmed for 1990.
|
||||
|
||||
### VE's To Be Incorporated Later
|
||||
|
||||
* Wire feeders ILO busduct
|
||||
|
||||
### Feeders
|
||||
|
||||
Fire pump feeds are not tagged as 2hr rated
|
||||
takeoff assumed 2hr rated MC cable ("Vitalink")
|
||||
to be confirmed with Christian.
|
||||
|
||||
### EV Chargers
|
||||
|
||||
EV Chargers were erroneously placed in `System` "EL - Electrical".
|
||||
|
||||
### Lighting Controls
|
||||
|
||||
Josh was looking for for energy code
|
||||
not present in pre-takeoff email or OneNote.
|
||||
|
||||
ASHRAE 2016
|
||||
|
||||
***
|
||||
|
||||
Follow-up to [[2026-03-26_08-49-49#Lighting Control Assemblies]].
|
||||
|
||||
Josh confirmed the switch to complete-furnish assemblies was appropriate.
|
||||
|
||||
### Labor Plan
|
||||
|
||||
Garage Slab/Deck is $1.30/sf
|
||||
where $1.00/sf was expected.
|
||||
Josh attributes this mainly to the EV chargers and CO system.
|
||||
|
||||
Innerduct: Use 3hrs per Unit.
|
||||
|
||||
### Scratch
|
||||
|
||||
Composite Cleanup is based on 8hrs per week for every 10 crew
|
||||
|
||||
Coordination Study: Expect $15k per $10m of switchgear package
|
||||
|
||||
#### Temporary Lighting
|
||||
|
||||
Temp lighting budget does not include heating
|
||||
or lighting in units ("task lighting")
|
||||
|
||||
#### Rigging
|
||||
|
||||
3rd party rigging quotes are only for special cases.
|
||||
It is expected that the GC's crane
|
||||
can be used to set switchboards and generators.
|
||||
|
||||
On 1990, the GC (Clarke) RFP provides 16 hours crane time.
|
||||