# 2026-03-26 08:49:49
|
||||
|
||||
## 1990 K Street Senior Review
|
||||
|
||||
Follow-up to [[2026-03-20_13-44-59#2026-03-20 13:44:59]].
|
||||
|
||||
Comments by Joel Jansen
|
||||
Relevant to my takeoff for [[1990-k-street]]:
|
||||
|
||||
### Lighting Control Assemblies
|
||||
|
||||
Relevant to [[lighting-controls-takeoff]]:
|
||||
|
||||
Lighting control assembly selection for the project was contentious
|
||||
because PDS excluded the system due to lack of information,
|
||||
but the drawings painted as exact a picture as one could ask for prior to construction.
|
||||
|
||||
> Design shows digital control, dimming controlled by occ sensors in stairwells, corridors. \
|
||||
> ---E021 AUTOMATED LIGHTING CONTROL - SEQUENCES OF OPERATIONS
|
||||
>
|
||||
> Proposal excludes digital lighting control due to lack of information. \
|
||||
> ---Proposal 2026-01-22, Pricing Alternates
|
||||
>
|
||||
> Spec 260923 - LIGHTING CONTROL DEVICES \
|
||||
> Spec 260936 - MODULAR DIMMING CONTROLS
|
||||
|
||||
In conversation with Joel,
|
||||
we agreed that I would use the "FBO" assemblies
|
||||
with the assumption that an LV system would be budgeted.
|
||||
|
||||
> [!quote] 1990 K Street ConEst OneNote, "Lighting Control"
|
||||
> Takeoff to use FBO assemblies (rough-in, cable, and device labor). \
|
||||
> ---Joel Jansen 2026-02-11 11:05
|
||||
|
||||
After direction I'm not clear on,
|
||||
Joel switched these to the device labor and material assemblies.
|
||||
|
||||
[[lighting-controls-research]]
|
||||
|
||||
### Feeder Schedule 5"C
|
||||
|
||||
Relevant to [[feeders-takeoff]]:
|
||||
|
||||
Feeder schedule calls for 5 inch conduit for certain tags
|
||||
which PDI's schedule uses 4 inch for.
|
||||
I did not respect this in the takeoff,
|
||||
Joel intends to substitute.
|
||||
|
||||
***
|
||||
|
||||
**\[2026-03-26 09:36\]**
|
||||
After conversation with Christian,
|
||||
Joel substituted all EMT feeders for MC cable.
|
||||
Christian stated that [[pdi-estimating#Bid Estimating|they]]
|
||||
would qualify the substitution in their next proposal
|
||||
and raised that 5 inch EMT does not exist in our database anyway[^1].
|
||||
|
||||
[^1]: It doesn't exist at all.
|
||||
See [[nfpa-70_358_emt#358.20(B) Maximum.|NEC 358.20(B)]].
|
||||
|
||||
Reference in New Issue
Block a user