@@ -8,27 +8,36 @@ daily: "[[2026-04-27]]"
## Virginia Live! Internal Review
[[virginia-live-casino-and-hotel]]
review of [[virginia-live-casino-and-hotel]] [[accubid|Accubid]] job
with [[pdi-operations|Ops]]
Underfloor power is Reloc.
Customer is curious if it would be more cost effective to use MC.
Objective is to discuss closeout mainly:
### Meeting Objective
discuss closeout mainly:
quotes and subs.
FF&E
### Topics Discussed
#### Fixture Labor
> **Furniture, Fixtures, and Equipment (FF&E)**
Concern that all fixtures are captured
"add a line for aiming and testing"
1 week (80 hours)
Shift rate
#### Shift Rate
"in the past we've paid a little more for night work,
but nothing crazy"
$2,500 per day scaffold
#### Site Services
### Site Services
$2,500 per day scaffold
Ditch witches for most excavation
@@ -40,7 +49,7 @@ hydraulic bender
Do we own dewatering?
pretty sure yes
### MV Terminations
#### MV Terminations
No one at PDI can perform MV terms
so they must be subbed out
@@ -51,7 +60,7 @@ worst case $300k
to be quoted by Ops
### Testing
#### Testing
primary injection testing
@@ -59,25 +68,25 @@ NETA testing
to be quoted by Ops
### Rigging
#### Rigging
Ops quoted $85k to take one generator off the truck.
to be quoted by Ops
### Burden
#### Burden
PTO not included in burden
because it is not charged to the job
### Admin Housing
Ops paying $4,500 for 6-bed
Ops paying $4,500 per month for 6-bed
### Composite Cleanup
#### Composite Cleanup
terms in contract
exact terms in contract
### Permits
#### Permits
to be quoted by Ops