@@ -84,7 +84,8 @@ Alternative
## Telecom Backboard
As shown on plans, only if not excluded in pro
As shown on plans,
only if not excluded in proposal.
1. * `Phase` = "Building - BOH ..."
* `System` = "TC - Telecom Backbone"
@@ -108,7 +109,7 @@ For future use (e.g. fiber)
* **Material Price** = 450.00/C
* **Labor Hours** = 12.00/C
Alternative
_Alternative:_
1. `COMMON ASSEMBLIES`/`TELECOM SYSTEMS`/`INNERDUCT`/`... (GP)`
@@ -123,5 +124,12 @@ Ignore scope shared with [[electrical-takeoff|electrical]].
* .../`SCREWLESS DECORA COVERS UNITS / BOH`
* .../`ROUGH IN ASSY`
If _system_ is included, take off _both_ rough-in and device assemblies
If _system_ is included,
take off _both_ rough-in and device assemblies
in amenity areas.
If rough-in is included,
always provide backboxes and conduit stub-ups for outlets in other than units,
even if qualified as "free-air per code" or similar.[^1]
[^1]: [[2026-03-25_08-14-59#"Free-Air Per Code"]]