@@ -162,6 +162,10 @@ For each stairwell:
## Devices
Takeoff should always(?) use the
`DOES NOT INCLUDE COST OF DEVICES AND CABLE` assemblies,
since we will always(?) have a fire alarm quote.
### Smoke Detectors
1. `COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`INITIATING DEVICES WITH WIRE - ...`/`SMOKE DETECTOR W/ BASE - ...`
@@ -190,11 +194,12 @@ For each stairwell:
_Design Build (method 1):_
* Count every 75 ft,
* measure with circles on Bluebeam
* or divide relevant SF area by 4415
* $\pi(\frac{75}{2})^2 \approx 4415$
* or divide relevant SF area by 4415[^2]
* every elevator lobby, and
* every BOH room on the first floor and garage levels.
[^2]: $\pi(\frac{75}{2})^2 \approx 4415$
_Design Build (alternative method):_
* 15ft from end of corridor,
* then every 50ft