# 2026-06-04 13:20:08
|
||||
|
||||
## 303 Mariposa Residence
|
||||
|
||||
[[conest-manager-review]] for [[303-mariposa-residence]]
|
||||
lead by [[josh-ford]] as ConEst Manager
|
||||
attended by [[joel-jansen]] as ConEst Senior Estimator
|
||||
and [[jared-defanti]] and [[zane-meyers]] as ConEst Estimators.
|
||||
|
||||
### Temporary Power
|
||||
|
||||
> "Do they really need \$10,000 for temp power?"
|
||||
|
||||
\$2,500 and 50hrs
|
||||
|
||||
### Site Lighting
|
||||
|
||||
Pole Bases
|
||||
|
||||
> "I would leave it if it's for the bollards. It can't be that much."
|
||||
|
||||
### Site Low Voltage Duct Bank
|
||||
|
||||
Josh okayed assumptions for site runs
|
||||
secondaries
|
||||
|
||||
### Putty Pads
|
||||
|
||||
add putty pads equal to device boxes
|
||||
|
||||
### Feeders
|
||||
|
||||
%% is run from inverter to EM diff size from MDP to inverter? %%
|
||||
|
||||
### Dimmable Receptacles
|
||||
|
||||
> Lutron Homeworks devices are thicker,
|
||||
> need deep boxes.
|
||||
|
||||
### Lighting/Shade Controls
|
||||
|
||||
[[lighting-controls-takeoff]]
|
||||
|
||||
#### Trough
|
||||
|
||||
`COMMON ASSEMBLIES`/`DISTRIBUTION`/`LIGHTING CONTROL PANEL INSTALLATION`/`_ - LIGHTING CONTROL PANEL INSTALLATION & TROUGH - ...`
|
||||
|
||||
used 4 section
|
||||
changed labor time from 4 to 6
|
||||
added 500ft \#12/2 NM
|
||||
|
||||
### Telecom
|
||||
|
||||
> "I'm surprised this isn't a certified system"
|
||||
|
||||
Changed assumed Cat5e to Cat6
|
||||
|
||||
> "I feel like we don't ever install Cat5 anymore"
|
||||
>
|
||||
> "A house on the upper range like this isn't going to go with Cat5"
|
||||
|
||||
AV Coordination.pdf
|
||||
TV Specs: 3 Cat6
|
||||
|
||||
### Fire Alarm
|
||||
|
||||
Leaving smokes despite direction
|
||||
for budgetary purposes.
|
||||
|
||||
### Closeout
|
||||
|
||||
#### Labor Plan
|
||||
|
||||
> "I don't think you can even do a labor plan."
|
||||
> "Just leave it all at 100%."
|
||||
|
||||
> "I use World (Electric) for everything, I don't care where it is."
|
||||
|
||||
#### Subs
|
||||
|
||||
Excavation $5,000
|
||||
|
||||
Wireways, Troughs: $1,250
|
||||
|
||||
#### General Expenses
|
||||
|
||||
Lower Office Supplies to $2,500
|
||||
|
||||
Delete Customer Development
|
||||
|
||||
##### Duration
|
||||
|
||||
Approved Labor Plan says 16 months
|
||||
|
||||
Removed all under "Jobs > \$3mil COGs"
|
||||
|
||||
Josh said he removed COGs with Aaron's direction
|
||||
on a job sold at \$3.8 million.
|
||||
|
||||
#### Equipment
|
||||
|
||||
Removed two-way radio
|
||||
|
||||
#### Material Pricing
|
||||
|
||||
> Josh: "Put \$400 for the Quazite." \
|
||||
> Joel: "I put \$1,200." \
|
||||
> Josh: "You put \$1,200? Okay put \$500."
|
||||
|
||||
### Conclusion
|
||||
|
||||
surprised by high margin,
|
||||
checked bid takeoff
|
||||
found large cost difference in relocation budget
|
||||