303 Mariposa Residence

conest-manager-review for 303-mariposa-residence lead by josh-ford as ConEst Manager attended by joel-jansen as ConEst Senior Estimator and jared-defanti and zane-meyers as ConEst Estimators.

Temporary Power

"Do they really need $10,000 for temp power?"

$2,500 and 50hrs

Site Lighting

Pole Bases

"I would leave it if it's for the bollards. It can't be that much."

Site Low Voltage Duct Bank

Josh okayed assumptions for site runs secondaries

Putty Pads

add putty pads equal to device boxes

Feeders

%% is run from inverter to EM diff size from MDP to inverter? %%

Dimmable Receptacles

Lutron Homeworks devices are thicker, need deep boxes.

Lighting/Shade Controls

lighting-controls-takeoff

Trough

COMMON ASSEMBLIES/DISTRIBUTION/LIGHTING CONTROL PANEL INSTALLATION/_ - LIGHTING CONTROL PANEL INSTALLATION & TROUGH - ...

used 4 section changed labor time from 4 to 6 added 500ft #12/2 NM

Telecom

"I'm surprised this isn't a certified system"

Changed assumed Cat5e to Cat6

"I feel like we don't ever install Cat5 anymore"

"A house on the upper range like this isn't going to go with Cat5"

AV Coordination.pdf TV Specs: 3 Cat6

Fire Alarm

Leaving smokes despite direction for budgetary purposes.

Closeout

Labor Plan

"I don't think you can even do a labor plan." "Just leave it all at 100%."

"I use World (Electric) for everything, I don't care where it is."

Subs

Excavation $5,000

Wireways, Troughs: $1,250

General Expenses

Lower Office Supplies to $2,500

Delete Customer Development

Duration

Approved Labor Plan says 16 months

Removed all under "Jobs > $3mil COGs"

Josh said he removed COGs with Aaron's direction on a job sold at $3.8 million.

Equipment

Removed two-way radio

Material Pricing

Josh: "Put $400 for the Quazite."
Joel: "I put $1,200."
Josh: "You put $1,200? Okay put $500."

Conclusion

surprised by high margin, checked bid takeoff found large cost difference in relocation budget