# 2026-06-04 13:20:08
## 303 Mariposa Residence
[[conest-manager-review]] for [[303-mariposa-residence]]
lead by [[josh-ford]] as ConEst Manager
attended by [[joel-jansen]] as ConEst Senior Estimator
and [[jared-defanti]] and [[zane-meyers]] as ConEst Estimators.
### Temporary Power
> "Do they really need \$10,000 for temp power?"
\$2,500 and 50hrs
### Site Lighting
Pole Bases
> "I would leave it if it's for the bollards. It can't be that much."
### Site Low Voltage Duct Bank
Josh okayed assumptions for site runs
secondaries
### Putty Pads
add putty pads equal to device boxes
### Feeders
%% is run from inverter to EM diff size from MDP to inverter? %%
### Dimmable Receptacles
> Lutron Homeworks devices are thicker,
> need deep boxes.
### Lighting/Shade Controls
[[lighting-controls-takeoff]]
#### Trough
`COMMON ASSEMBLIES`/`DISTRIBUTION`/`LIGHTING CONTROL PANEL INSTALLATION`/`_ - LIGHTING CONTROL PANEL INSTALLATION & TROUGH - ...`
used 4 section
changed labor time from 4 to 6
added 500ft \#12/2 NM
### Telecom
> "I'm surprised this isn't a certified system"
Changed assumed Cat5e to Cat6
> "I feel like we don't ever install Cat5 anymore"
>
> "A house on the upper range like this isn't going to go with Cat5"
AV Coordination.pdf
TV Specs: 3 Cat6
### Fire Alarm
Leaving smokes despite direction
for budgetary purposes.
### Closeout
#### Labor Plan
> "I don't think you can even do a labor plan."
> "Just leave it all at 100%."
> "I use World (Electric) for everything, I don't care where it is."
#### Subs
Excavation $5,000
Wireways, Troughs: $1,250
#### General Expenses
Lower Office Supplies to $2,500
Delete Customer Development
##### Duration
Approved Labor Plan says 16 months
Removed all under "Jobs > \$3mil COGs"
Josh said he removed COGs with Aaron's direction
on a job sold at \$3.8 million.
#### Equipment
Removed two-way radio
#### Material Pricing
> Josh: "Put \$400 for the Quazite." \
> Joel: "I put \$1,200." \
> Josh: "You put \$1,200? Okay put \$500."
### Conclusion
surprised by high margin,
checked bid takeoff
found large cost difference in relocation budget