id: electrical
aliases: []
tags:
- systems/electrical
---
# Electrical
## Sequence
### 1. Estimate preparation
2. Read about the project specifications and construction type
3. Locate Equipment Schedules
4. Device specs (Decora or Standard)
### 2. Takeoff
1. Takeoff all equipment that is not #12
2. Go by Drawing in chronological order
3. Takeoff Enlarged Drawings
4. Do final checklist in electrical takeoff notes
> [!tip]
> It is sometimes easier to rebuild a designation than to modify it.
> For designations with existing takeoffs, Right-Click > `Empty Designation`.
> The build process can then be completed anew.
### 3. Extension (Review and Checking)
1. Count Car chargers and location
## Takeoff
### Lighting Control
By PDI convention, [[lighting-controls]] are generally "Electrical", not "Lighting".
### Receptacles
### Mechanical Connections
#### CU/IP
* Units Condensing Unit
* Mechanical Connection
#### Trash Chute
Horizontal:
* Check if shown on power drawings as mech connection
* If not, use 100ft length
Vertical (Riser):
* Takeoff: `COMMON ASSEMBLIES`/`MISC ASSEMBLIES`/`TRASH CHUTE RISER CIRCUIT...`
* Uncheck Link 'Enable Livecount'
* Takeoff in Typical
* Length = average floor to floor height