@@ -38,9 +38,11 @@ Match Fire Alarm takeoff Length and Count
|
||||
|
||||
### Stairwell Riser Every 2 Floors
|
||||
|
||||
`Area` = "Typical - Building Even Levels"
|
||||
|
||||
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`STAIRWELL RISER EVERY 2 FLRS = ...`
|
||||
> [!info] Takeoff
|
||||
> * `Area` = "Typical - Building Even Levels"
|
||||
>
|
||||
> 1. `COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`STAIRWELL RISER EVERY 2 FLRS = ...`
|
||||
> * **Count** = Each stairwell
|
||||
|
||||
### FACR to Electric Room
|
||||
|
||||
@@ -56,9 +58,9 @@ Takeoff in every Electric Room
|
||||
|
||||
### Top 2H Rated Room To Roof
|
||||
|
||||
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`TOP 2HR RATED RM TO ROOF = ...`
|
||||
|
||||
* **Length** = 15ft or height of ceiling on last building level
|
||||
> [!info] Takeoff
|
||||
> 1. `COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`TOP 2HR RATED RM TO ROOF = ...`
|
||||
> * **Length** = 15ft or height of ceiling on last building level
|
||||
|
||||
## Horizontal
|
||||
|
||||
@@ -66,6 +68,6 @@ Takeoff in every Electric Room
|
||||
> Usually only for cellular DAS.
|
||||
> Confirm takeoff requirement with [[pdi-estimating#Bid Estimating|Bid]].
|
||||
|
||||
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`CORRIDORS ...`
|
||||
|
||||
* **Length** = Length measured for every corridor/garage
|
||||
> [!info] Takeoff
|
||||
> 1. `COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`CORRIDORS ...`
|
||||
> * **Length** = Length measured for every corridor/garage
|
||||
|
||||