# 2026-01-12 13:02:??
|
||||
|
||||
#topic/construction
|
||||
|
||||
**Dry utilities:** utilities other than "wet" utilities (water, sewer, stormwater),
|
||||
namely power, data, and natural gas.
|
||||
|
||||
# 2026-01-12 13:02:??
|
||||
|
||||
#occupational
|
||||
|
||||
Joel attributes the [[#GP Variance|apparent variance]] to
|
||||
1. missed Polaris lugs for feeders for one building,
|
||||
2. insufficient budget for equipment rental, and
|
||||
3. upfront costs already paid (construction is 50% complete).
|
||||
|
||||
He also said that operations accused ConEst
|
||||
of providing insufficient length for subfeeds,
|
||||
which he said was true,
|
||||
but not to the extent accused
|
||||
(only ~600ft missed total).
|
||||
|
||||
The award WBS shows $32,382 for equipment rental
|
||||
|
||||
I'm dubious of all these explanations,
|
||||
but I don't have another one.
|
||||
I can't find the ConEst folder or Accubid file.
|
||||