## Create a WBS
|
||||
@@ -66,7 +67,8 @@ Once received, validation no longer required
|
||||
* Create Accubid file in proper location and format
|
||||
* Create LiveCount folder in proper location and format
|
||||
* Enter WBS area breakout and Unit Matrix into Accubid
|
||||
* Upload contracted plans per scope of work to LiveCount and tie to Accubid using standard bookmark instructions
|
||||
* Upload contracted plans per scope of work to LiveCount
|
||||
and tie to Accubid using standard bookmark instructions
|
||||
|
||||
### Grading Scale
|
||||
|
||||
@@ -122,7 +124,9 @@ Once received, validation no longer required
|
||||
|
||||
### Requirements
|
||||
|
||||
* Review reflected ceiling plans and compare/cross reference architectural, electrical, interior design, and landscape plans to identify all fixtures and their proper mounting requirements and length per fixture.
|
||||
* Review reflected ceiling plans and compare/cross reference
|
||||
architectural, electrical, interior design, and landscape plans
|
||||
to identify all fixtures and their proper mounting requirements and length per fixture.
|
||||
Fixture schedule may be required to consult for mounting requirements.
|
||||
* Build fixture assembly and assign to proper Accubid task
|
||||
|
||||
|
||||