@@ -12,14 +12,14 @@ of arbitrarily requiring components or methods far more stringent than typical.
|
||||
In [[construction-estimating]],
|
||||
such cases quickly reveal every error of assumption made by the estimator.
|
||||
|
||||
## Example: Aluminum Feeders ILO Copper
|
||||
|
||||
The typical value engineering option for electrical installations
|
||||
is to use aluminum wiring in lieu of copper above a certain size.
|
||||
Assuming competent installation, such an option is strictly functionally equal to the design.
|
||||
There is _no_ difference to capacity, future expansion, or long-term maintenance.
|
||||
Moreover, the substitution is invisible to the client,
|
||||
such that they would have to employ an electrician
|
||||
to determine whether it had been taken.
|
||||
Despite this, copper wiring is still a common specification default
|
||||
because clients care about that sort of thing for some reason.
|
||||
> [!example] Aluminum Feeders ILO Copper
|
||||
> The typical value engineering option for electrical installations
|
||||
> is to use aluminum wiring in lieu of copper above a certain size.
|
||||
> Assuming competent installation,
|
||||
> such an option is strictly functionally equal to the design.
|
||||
> There is _no_ difference to capacity, future expansion, or long-term maintenance.
|
||||
> Moreover, the substitution is invisible to the client,
|
||||
> such that they would have to employ an electrician
|
||||
> to determine whether it had been taken.
|
||||
> Despite this, copper wiring is still a common specification default
|
||||
> because clients care about that sort of thing for some reason.
|
||||
|
||||