vault backup: 2025-11-12 16:49:17
This commit is contained in:
@@ -26,6 +26,9 @@ Determine which Systems and Codes are required:
|
||||
|
||||
## PDI Lighting Control Configurations
|
||||
|
||||
> [!important]
|
||||
> This section is currently not practical
|
||||
|
||||
### Stand Alone
|
||||
|
||||
0-10V dim -- "LV cable" is 2 conductor
|
||||
@@ -42,19 +45,19 @@ Takeoff homeruns to the DLM (one per controlled circuit)
|
||||
|
||||
### Networked
|
||||
|
||||
#### Devices
|
||||
"LV Cable" is [[twisted-pair-cable]]
|
||||
|
||||
##### Room Controllers
|
||||
#### Room Controllers
|
||||
|
||||
No room controllers are necessary,
|
||||
lighting zones are switched from a central lighting control panel (LCP)
|
||||
|
||||
##### Switches and Sensors
|
||||
#### Switches and Sensors
|
||||
|
||||
Takeoff rough-in for switches and occupancy sensors
|
||||
|
||||
??
|
||||
(only if time based; length based on closeness to sw/occ sensor)
|
||||
(only if time based; length based on proximity to switch or occupancy sensor)
|
||||
??
|
||||
|
||||
#### Homeruns
|
||||
@@ -65,18 +68,26 @@ Takeoff 1 circuit homerun per lighting zone.
|
||||
|
||||
PDI default configuration
|
||||
|
||||
Takeoff (1) DLM controller for the fixtures
|
||||
and (1) Plug controller for the receptacle
|
||||
* If room has both dimmable fixtures and the controlled receptacle,
|
||||
only (1) DLM controller and (1) Plug controller
|
||||
* Use MC to cover room if drop
|
||||
* Use EMT if exposed or MC not permitted
|
||||
#### Room Controllers
|
||||
|
||||
For all rooms with dimmable fixtures
|
||||
and/or automatically controlled receptacles,
|
||||
take off (1) of either or both as appropriate.
|
||||
|
||||
`SWITCHES`/`LOW VOLTAGE SWITCHES & OCC SENSORS - ROUGH IN`/`DLM LTG RM CONTROLLER - ...`
|
||||
|
||||
`SWITCHES`/`LOW VOLTAGE SWITCHES & OCC SENSORS - ROUGH IN`/`REC PLUG CONTROLLER - ...`
|
||||
|
||||
Takeoff normal power to the controlled load
|
||||
* Add LV cable to fixture branch
|
||||
* Use 12/3 for receptacles
|
||||
* Use \#12/3 for controlled receptacles
|
||||
|
||||
Takeoff rough-in for both the occ sensors and the LV switch
|
||||
|
||||
`SWITCHES`/`LOW VOLTAGE SWITCHES & OCC SENSORS - ROUGH IN`/`... LV SW - WALL ROUGH IN ...`
|
||||
|
||||
`SWITCHES`/`LOW VOLTAGE SWITCHES & OCC SENSORS - ROUGH IN`/`... SENSOR LOW VOLTAGE - ROUGH IN ...`
|
||||
|
||||
* Free air if possible
|
||||
* **Length** = length of room
|
||||
|
||||
@@ -90,7 +101,14 @@ If occupancy sensors are shown in the corridors:
|
||||
Takeoff homerun back to the electric room
|
||||
|
||||
Takeoff (1) DLM controller for each electric room
|
||||
* Run free air down corridor
|
||||
|
||||
`SWITCHES`/`LOW VOLTAGE SWITCHES & OCC SENSORS - ROUGH IN`/`DLM LTG RM CONTROLLER - ...`
|
||||
|
||||
??
|
||||
Run free-air down corridor
|
||||
??
|
||||
|
||||
* **Length** = Length of corridor
|
||||
|
||||
Takeoff rough-in for each occupancy sensor shown.
|
||||
|
||||
|
||||