@@ -85,8 +85,7 @@ Would I be better of keeping my mouth shut about it?
|
||||
#### Incentives
|
||||
|
||||
Bonuses based on awarded profit
|
||||
incentivize problematic behavior
|
||||
([[game-theory#Stag Hunt|hare-hunting]]).
|
||||
incentivize problematic [[stag-hunt|hare-hunting]] behavior.
|
||||
Has such behavior been observed,
|
||||
or has chief strategy been organization-aligned
|
||||
in spite of the incentive to defect?
|
||||
|
||||
@@ -0,0 +1,98 @@
|
||||
---
|
||||
id: 2026-05-25T15:02:03-0400
|
||||
title: 2026-05-25 15:02:03
|
||||
tags: []
|
||||
daily: "[[2026-05-25]]"
|
||||
---
|
||||
# 2026-05-25 15:02:03
|
||||
|
||||
The perceived value of detailed takeoff is baffling
|
||||
because its single advantage over reference class forecasting
|
||||
(which offers innumerable advantages over detailed takeoff)
|
||||
is in itemized pricing,
|
||||
but this advantage is nullified
|
||||
by the known phenomenon that the precise
|
||||
selection of particular items and their quantities
|
||||
can not be trusted to be exactly accurate
|
||||
due to uncertainty of project conditions,
|
||||
and by the observation that material pricing at the time of bid
|
||||
is not representative of the cost of buyout.
|
||||
|
||||
The inevitable retort is
|
||||
"It's an *est*imate, not an *exact*imate,"
|
||||
or some other such reductive dismissal.
|
||||
True enough, this method is _a_ way
|
||||
of getting close to the true answer of project cost and schedule,
|
||||
but it's not an intuitive one.
|
||||
|
||||
For an organizational process to be economical
|
||||
it must contribute value greater than its cost.
|
||||
Reduction of loss (risk mitigation) is a form of value,
|
||||
and is the vector by which detailed takeoff is expected to be economical:
|
||||
a more confident estimate (a narrower high-confidence interval)
|
||||
allows the organization to bid more aggressively (bid lower)
|
||||
without increasing their assumed risk in project execution.
|
||||
A lower bid increases the probability of award,
|
||||
decreasing the risk that estimating resources will have been wasted.
|
||||
We can assume that this is not the vector by which _[[conest|ConEst]]_
|
||||
is expected to generate value,
|
||||
both because it does not appear to be effective in this regard[^1]
|
||||
and because the ConEst estimate is not used as basis to decrease the bid.[^2]
|
||||
|
||||
[^1]: See [[2026-05-22_11-57-18]].
|
||||
|
||||
[^2]: This may be missed opportunity.
|
||||
My baseless (and perhaps naive) speculation
|
||||
is that a "Hey, we took a closer look and got our price down a bit more"
|
||||
may indicate to the customer a [[stag-hunt|stag hunting]] behavior
|
||||
that is more valuable than the real decrease in expected profit.
|
||||
|
||||
As an estimating method,
|
||||
detailed takeoff is not more _precise_
|
||||
(its use does not significantly decrease our certainty),
|
||||
but it is more _granular_.
|
||||
An estimate based on detailed takeoff can be easily[^3] subdivided
|
||||
for use in [[earned-value-management]],
|
||||
but its most immediate use is in identifying variation
|
||||
from the expected case.
|
||||
In other words,
|
||||
deciding when overruns can be blamed on mismanagement,
|
||||
and when they are simply bad luck.
|
||||
|
||||
[^3]: Depending on the takeoff software.
|
||||
|
||||
The last case is where I'd bet the perceived value of ConEst is found.[^4]
|
||||
I can't help but feel that this effort is misplaced.
|
||||
If project management is like estimating,
|
||||
I have no doubt that they could _all_ benefit from training.
|
||||
Identifying who exactly needs it more, then, is pointless.
|
||||
As well to identify which cases of great project success
|
||||
can actually be attributed to exceptional management
|
||||
and not simply [[the-failure-of-risk-management#Red Baron Effect|the Red Baron effect]].
|
||||
|
||||
[^4]: Crew loading and schedule are important points in estimating,
|
||||
and EVM is a fine solution there,
|
||||
but it would be straightforward to apply the same RCF principles
|
||||
that we use for Bid estimates for these as well.
|
||||
That we use detailed takeoff in lieu of such methods
|
||||
suggests that it is believed necessary for other reasons.
|
||||
|
||||
***
|
||||
|
||||
Working exclusively in multifamily for this time
|
||||
has lead me to spend a lot of time thinking about the question
|
||||
of how estimating resources are best allocated.
|
||||
My understanding of the industry is that,
|
||||
despite the apparent focus on cost,
|
||||
executive focus is usually on maintaining a consistent volume of work.
|
||||
Because as contractors we are thinly-capitalized,[^5]
|
||||
failing to do so seems to represent a larger risk
|
||||
than a low-margin contract.
|
||||
Under these conditions,
|
||||
estimating has very little to do with the project itself,
|
||||
so we can make assumptions about it
|
||||
that might not normally seem appropriate.
|
||||
It is because of our narrow market
|
||||
that we get to have these much more interesting discussions.
|
||||
|
||||
[^5]: See [[merrow_2022_contract-strategies]].
|
||||