@@ -28,4 +28,86 @@ Drawings show 2 separate duplex receptacles for dishwasher and disposal
|
||||
Takeoff used `DW & DISPOSAL DUAL CIR - ...`,
|
||||
which includes only one receptacle.
|
||||
|
||||
According to Joel this takeoff is correct for the scenario.
|
||||
According to Joel this takeoff is correct for the scenario.
|
||||
|
||||
## 2026-01-12 12:23
|
||||
|
||||
Travelling with Brian Smarslok and Joel Jansen on [[2026-01-15]]
|
||||
to visit [[#Woodbury Heights|an awarded project]] in New Jersey.
|
||||
Flying from TPA to PHL, departure @ 7:00AM.
|
||||
We'll be meeting with the developer, [Greystar](https://www.greystar.com/).
|
||||
|
||||
### Woodbury Heights
|
||||
|
||||
```yaml
|
||||
project-name: GSC Ltd. Woodbury Heights (aka Academy Pointe)
|
||||
sector: Residential
|
||||
market-type: Apartment
|
||||
bldg-type: Garden
|
||||
construction-method: Wood Frame
|
||||
construction-type: V
|
||||
unit-wiring-method: Romex
|
||||
code-data: NEC2020
|
||||
mech-system: Split Dx
|
||||
buildings: 9
|
||||
floors: 3
|
||||
units: 234
|
||||
gross-area: 266,272
|
||||
area-by-type:
|
||||
- exterior-amenity: 12,306
|
||||
- interior-amenity: 5,031
|
||||
- garage: 3,788
|
||||
- saleable: 223,172
|
||||
division: MA 1
|
||||
geographic-region: Northeast
|
||||
metro-area: New York-Newark-Jersey City, NY-NJ-PA
|
||||
municipality-or-ahj: City of Woodbury
|
||||
power-company: PSE&G
|
||||
stakeholders:
|
||||
- developer: Greystar (HQ - Charleston, SC)
|
||||
architect: LS3P Associates Ltd
|
||||
electrical-engineer: Hurst Engineering
|
||||
contract-value: 2,305,000.00
|
||||
start-date: 2025-05-01
|
||||
end-date: 2026-08-26
|
||||
duration: 11 months
|
||||
```
|
||||
|
||||
#### GP Variance
|
||||
|
||||
"GP%" is **margin** (see [[markup-vs-margin]]).
|
||||
|
||||
The job appears to be doing poorly, at current GP variance of -$299,356.
|
||||
|
||||
About $93,000.00 profit on a $2,391,378 job (~3% margin, down from 16.4% as bid).
|
||||
|
||||
Intend to ask Joel what was missed if he knows,
|
||||
and more generally if he has a strategy for figuring out,
|
||||
between BPM, The Hub, and however many other places we can look.
|
||||
|
||||
I doubt very seriously that mismanagement
|
||||
can be blamed for any significant portion of variance that extreme.
|
||||
|
||||
## 2026-01-12 13:02
|
||||
|
||||
**Dry utilities:** utilities other than "wet" utilities (water, sewer, stormwater),
|
||||
namely power, data, and natural gas.
|
||||
|
||||
## 2026-01-12 13:02
|
||||
|
||||
Joel attributes the [[#GP Variance|apparent variance]] to
|
||||
1. missed Polaris lugs for feeders for one building,
|
||||
2. insufficient budget for equipment rental, and
|
||||
3. upfront costs already paid (construction is 50% complete).
|
||||
|
||||
He also said that operations accused ConEst
|
||||
of providing insufficient length for subfeeds,
|
||||
which he said was true,
|
||||
but not to the extent accused
|
||||
(only ~600ft missed total).
|
||||
|
||||
The award WBS shows $32,382 for equipment rental
|
||||
|
||||
I'm dubious of all these explanations,
|
||||
but I don't have another one.
|
||||
I can't find the ConEst folder or Accubid file.
|
||||
|
||||