vault backup: 2025-12-10 15:58:11
This commit is contained in:
+19
-15
@@ -1,51 +1,55 @@
|
||||
---
|
||||
id:
|
||||
aliases: []
|
||||
title: 2025-11-04
|
||||
tags:
|
||||
- authorship/original
|
||||
- destiny/permanent
|
||||
- status/complete
|
||||
- type/minutes
|
||||
title: 2025-11-04 Belle Meade Director Review
|
||||
---
|
||||
# 2025-11-04 Belle Meade Director Review
|
||||
# 2025-11-04
|
||||
|
||||
## Takeoff Review
|
||||
## 2025-11-04 Belle Meade Director Review
|
||||
|
||||
#occupational
|
||||
|
||||
### Takeoff Review
|
||||
|
||||
Reviewed takeoff by system.
|
||||
|
||||
### Retail Village Temporary Power
|
||||
#### Retail Village Temporary Power
|
||||
|
||||
Joel changed square foot budgets to temporary pole budgets only
|
||||
due to minimal scope (warm shell).
|
||||
|
||||
### Generator Scope
|
||||
#### Generator Scope
|
||||
|
||||
Confirmed generator quotes include furnishing docking station.
|
||||
|
||||
### Feeder Lengths
|
||||
#### Feeder Lengths
|
||||
|
||||
Confirmed validity of longer feeder lengths:
|
||||
Generator to Tower B
|
||||
|
||||
### Grounding
|
||||
#### Grounding
|
||||
|
||||
Takeoff appears to be missing some or all grounding.
|
||||
To be added if necessary.
|
||||
|
||||
### Subfeed Sizing
|
||||
#### Subfeed Sizing
|
||||
|
||||
Based on ampacity, subfeeds are oversized.
|
||||
Sizing was per feeder schedule.
|
||||
Takeoff approved unchanged.
|
||||
|
||||
### Undercabinet Wiremold
|
||||
#### Undercabinet Wiremold
|
||||
|
||||
Multi-outlet assemblies above unit kitchen countertops were not taken off,
|
||||
nor was branch wiring for the same.
|
||||
Joel to confirm takeoff requirement with bid.
|
||||
|
||||
### Amenity Homeruns
|
||||
#### Amenity Homeruns
|
||||
|
||||
No homeruns for amenity lighting or electrical were taken off.
|
||||
Joel to add these.
|
||||
@@ -54,7 +58,7 @@ Joel to add these.
|
||||
> Corwin stated that---assuming no overriding specification---
|
||||
> up to 6 circuits in a raceway are permissible.
|
||||
|
||||
### Lighting Control
|
||||
#### Lighting Control
|
||||
|
||||
Lighting control takeoff was reviewed,
|
||||
no changes were recommended.
|
||||
@@ -65,18 +69,18 @@ no changes were recommended.
|
||||
> noting quantities of lighting zones and controllers,
|
||||
> even where not explicitly shown.
|
||||
|
||||
### Telecom
|
||||
#### Telecom
|
||||
|
||||
Confirmed unit telecom requirements.
|
||||
|
||||
Backbone was mistakenly taken off in Telecom.
|
||||
|
||||
### Retail Fire Alarm
|
||||
#### Retail Fire Alarm
|
||||
|
||||
Retail village fire alarm devices were taken off free-air,
|
||||
Joel to substitute for EMT.
|
||||
|
||||
## Extension Review
|
||||
### Extension Review
|
||||
|
||||
Reviewed extension quantities and costs.
|
||||
Of particular note were:
|
||||
@@ -86,7 +90,7 @@ Of particular note were:
|
||||
* cable
|
||||
* wiring devices
|
||||
|
||||
## Labor Plan Review
|
||||
### Labor Plan Review
|
||||
|
||||
Hours per square foot was lower than expected,
|
||||
this was rationalized as being due
|
||||
|
||||
Reference in New Issue
Block a user