id: electrical
|
||||
aliases: []
|
||||
title: Electrical Takeoff
|
||||
tags:
|
||||
- authorship/original
|
||||
- destiny/permanent
|
||||
- occupational/takeoff/electrical
|
||||
- status/draft
|
||||
- type/guide
|
||||
title: Electrical Takeoff
|
||||
---
|
||||
# Electrical Takeoff
|
||||
|
||||
@@ -28,24 +28,29 @@ In precast slab garages, use EMT.
|
||||
|
||||
## Lighting Control
|
||||
|
||||
By PDI convention, [[lighting-controls-takeoff]] are generally "Electrical", not "Lighting".
|
||||
See [[lighting-controls-takeoff]].
|
||||
|
||||
## Receptacles
|
||||
|
||||
## Floor Boxes
|
||||
|
||||
`COMMON ASSEMBLIES`/`FLOOR BOXES`/...
|
||||
|
||||
### Poke-Thru's
|
||||
|
||||
Use suitable floor box assembly,
|
||||
delete floor box items,
|
||||
add `ITEM DATABASE`/`WIRING & SYSTEM DEVICES`/`FLOOR BOXES & FITTTINGS`/`GENERIC - FLOOR BOXES & ACCESS`/`POKE-THRU W/ DUPLEX RECEPTACLE`
|
||||
|
||||
## Homeruns
|
||||
|
||||
### Lighting
|
||||
|
||||
Takeoff homeruns in Building breakdowns,
|
||||
even serving Amenity spaces.
|
||||
* `Area` = "XX - Level XX Building"
|
||||
* `Phase` = "Building - Back of House (BOH)"
|
||||
|
||||
> [!info] Breakdowns
|
||||
> * `Area` = "... Building"
|
||||
> * `System` = "Building - BOH ..."
|
||||
Takeoff homeruns in Building breakdowns,
|
||||
even where serving Amenity spaces.
|
||||
|
||||
## Mechanical Connections
|
||||
|
||||
@@ -58,7 +63,7 @@ per [[fire-resistive-wiring-methods-takeoff]].
|
||||
|
||||
### Roof Mounted Equipment
|
||||
|
||||
Unit condensing units
|
||||
#### Unit Condensing Units
|
||||
|
||||
Put homeruns on the `Area` of the dwelling unit.
|
||||
Put connections on the `Area` of the CU.
|
||||
@@ -79,18 +84,22 @@ Routed up through the roof,
|
||||
(optionally through a disconnect)
|
||||
with flex to the equipment.
|
||||
|
||||
Equipment Racks: Max 20 disconnects per rack
|
||||
#### Equipment Racks
|
||||
|
||||
Max 20 disconnects per rack
|
||||
|
||||
`DISTRIBUTIION`/`TRAPEZE RACK SUPPORT ...`/`...`
|
||||
|
||||
### Trash Chute
|
||||
|
||||
**Horizontal:**
|
||||
* Check if shown on power drawings as mech connection
|
||||
* If not, use 100ft length
|
||||
1. **Horizontal:**
|
||||
|
||||
**Vertical (Riser):**
|
||||
* Takeoff: `COMMON ASSEMBLIES`/`MISC ASSEMBLIES`/`TRASH CHUTE RISER CIRCUIT...`
|
||||
* Uncheck Link 'Enable Livecount'
|
||||
* Takeoff in Typical
|
||||
* Length = average floor to floor height
|
||||
`COMMON ASSEMBLIES`/`MECHANICAL CONNECTIONS ...`/...
|
||||
* **Length** = Length per drawings, 100ft if not shown.
|
||||
|
||||
2. **Vertical (Riser):**
|
||||
|
||||
* `Area` = "Typical - Building All Levels"
|
||||
|
||||
Takeoff: `COMMON ASSEMBLIES`/`MISC ASSEMBLIES`/`TRASH CHUTE RISER CIRCUIT...`
|
||||
* Length = average floor to floor height
|
||||
|
||||