vault backup: 2025-07-23 16:43:54

This commit is contained in:
2025-07-23 16:43:54 -04:00
parent 4e829fa06c
commit bb19afeea3
21 changed files with 37060 additions and 64 deletions
+25 -24
View File
@@ -8,33 +8,33 @@ tags: []
## 1. Trash Chute
Horizontal:
- Check if shown on power drawings as mech connection
- If not, use 100ft length
* Check if shown on power drawings as mech connection
* If not, use 100ft length
Vertical (Riser):
- Takeoff: `COMMON ASSEMBLIES`/`MISC ASSEMBLIES`/`TRASH CHUTE RISER CIRCUIT...`
- Uncheck Link 'Enable Livecount'
- Takeoff in Typical
- Length = average floor to floor height
* Takeoff: `COMMON ASSEMBLIES`/`MISC ASSEMBLIES`/`TRASH CHUTE RISER CIRCUIT...`
* Uncheck Link 'Enable Livecount'
* Takeoff in Typical
* Length = average floor to floor height
## 2. CU/IP
- Units Condensing Unit
- Mechanical Connection
* Units Condensing Unit
* Mechanical Connection
## 3. Slab Deck
Create Area Typicals for every Concrete slab floor:
- 'All Building'
- 1 every level (Not Roof)
- HD: 1 Per Section
* 'All Building'
* 1 every level (Not Roof)
* HD: 1 Per Section
- 'All Garage'
- 1 every level
* 'All Garage'
* 1 every level
- Takeoff: `ITEM DATABASE`/`MISC PDI PRODUCT`/`MISC MATERIAL - SLAB/DECK & FEEDER`/`MISC MATERIAL - SLAB/DECK (NAILS, PAINT, TAPE, ETC = $250)`
- 1 Takeoff each Typical, Count = 1
* Takeoff: `ITEM DATABASE`/`MISC PDI PRODUCT`/`MISC MATERIAL - SLAB/DECK & FEEDER`/`MISC MATERIAL - SLAB/DECK (NAILS, PAINT, TAPE, ETC = $250)`
* 1 Takeoff each Typical, Count = 1
## 4. Temporary Power & Lighting
@@ -46,8 +46,9 @@ Phase = "Temp Power"
System = "TPS - Temp Power Service (Site)"
BidItem = "1 - Site"
```
Hoxton Hotel (aka Nashville Hotel)
- Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`TEMPORARY POWER - * SERVICE`
* Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`TEMPORARY POWER - * SERVICE`
### 4.2A Temp Lighting (Building)
@@ -58,12 +59,12 @@ System = "TPD - Temp Power Distribution (Gag. & Bldg.)"
BidItem = "3 - Building"
```
- Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`* - TEMPORARY LIGHTING / PWR PNL (PER BLDG AREA SFT)`
- *Count* = Building Size = Total GSF - Garage GSF
* Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`* - TEMPORARY LIGHTING / PWR PNL (PER BLDG AREA SFT)`
* _Count_ = Building Size = Total GSF - Garage GSF
Garden Styles:
- Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`TEMPORARY POWER - T POLE (EACH)`
- *Count* = 1 per 150' per building
* Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`TEMPORARY POWER - T POLE (EACH)`
* _Count_ = 1 per 150' per building
### 4.2B Temp Lighting (Garage)
@@ -74,8 +75,8 @@ System = "TPD - Temp Power Distribution (Gag. & Bldg.)"
BidItem = "3 - Building"
```
- Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`* - TEMPORARY LIGHTING / PWR PNL (PER BLDG AREA SFT)`
- *Count* = Garage SF
* Takeoff: `ITEM DATABASE`/`TEMPORARY POWER`/`* - TEMPORARY LIGHTING / PWR PNL (PER BLDG AREA SFT)`
* _Count_ = Garage SF
## 5. Irrigation pumps
@@ -86,5 +87,5 @@ System = `MISC - Site Miscellaneous`
BidItem = "1 - Site"
```
- (3) 3Phase 30A 200' Mech. Con.
- Append to name: "Irrigation Pump - "
* (3) 3Phase 30A 200' Mech. Con.
* Append to name: "Irrigation Pump - "