# Sequence
|
||||
|
||||
## Electrical
|
||||
|
||||
### 1. Estimate preparation
|
||||
|
||||
2. Read about the project specifications and construction type
|
||||
3. Locate Equipment Schedules
|
||||
|
||||
4. Device specs (Decora or Standard)
|
||||
|
||||
### 2. Takeoff
|
||||
|
||||
1. Takeoff all equipment that is not #12
|
||||
2. Go by Drawing in chronological order
|
||||
3. Takeoff Enlarged Drawings
|
||||
4. Do final checklist in electrical takeoff notes
|
||||
|
||||
### 3. Extension (Review and Checking)
|
||||
|
||||
1. Count Car chargers and location
|
||||
|
||||
## Feeders
|
||||
|
||||
### 1. Estimate preparation
|
||||
|
||||
Read about the project specifications and construction type
|
||||
|
||||
* Delivery Method: (Plans & Specs, Design Build, Design Assist, Preliminary Budget)
|
||||
* Deck thickness
|
||||
* Wiring method
|
||||
* Conductor material (Aluminum/Copper)
|
||||
|
||||
Locate:
|
||||
* Riser Diagram
|
||||
* Feeder Schedule (if present)
|
||||
* Main Electrical rooms and panel locations
|
||||
* Routing (if present)
|
||||
|
||||
### 2. Takeoff
|
||||
|
||||
* Choose a starting point on the riser
|
||||
* Determine wire & Conduit makeup (3Ph/1Ph, AL/CU, Conduit)
|
||||
* Measure off the length of the feed _ADDERS_
|
||||
* Square corners, use corridors if possible
|
||||
|
||||
Bus Duct
|
||||
|
||||
### 3. Extension (Review and Checking)
|
||||
|
||||
## Fire Alarm - Riser
|
||||
|
||||
### 1. Estimate preparation
|
||||
|
||||
1. Initial the OneNote
|
||||
2. Find Fire Alarm plans (If Applicable)
|
||||
3. Locate Fire Command Center (FCC)
|
||||
|
||||
### 2. Takeoff
|
||||
|
||||
1. Use the FA Riser Script
|
||||
2. Takeoff Devices
|
||||
|
||||
### 3. Extension (Review and Checking)
|
||||
|
||||
1. Sleeving for riser?
|
||||
2. Are Two-Way/DAS Included?
|
||||
|
||||
## Fire Alarm - Devices
|
||||
|
||||
### 1. Estimate preparation
|
||||
|
||||
2. Read about the project specifications and construction type
|
||||
3. Find FA drawings or where they are shown
|
||||
|
||||
### 2. Takeoff
|
||||
|
||||
1. Takeoff floor plans in order
|
||||
2. Takeoff enlarged drawings
|
||||
|
||||
### 3. Extension (Review and Checking)
|
||||
|
||||
8. Fire Smoke Dampers (FSD's) FA or electrical?
|
||||
9. Sleeving?
|
||||
|
||||
## Lighting
|
||||
|
||||
### 1. Estimate preparation
|
||||
|
||||
1. Read about the project specifications and construction type
|
||||
2. In drawings, locate:
|
||||
* Fixture Schedule
|
||||
* Reflected Ceiling Plans
|
||||
|
||||
### 2. Takeoff
|
||||
|
||||
1. Takeoff floor plans in order
|
||||
2. Takeoff enlarged drawings
|
||||
|
||||
### 3. Extension (Review and Checking)
|
||||
|
||||
1. Garage Homeruns
|
||||
2. Luminaire in Amenity Areas
|
||||
3. Ensure appropriate breakdowns
|
||||
* Site lighting in System =="Site Misc. Fixtures"==
|
||||
|
||||
## Units
|
||||
|
||||
### 1. Estimate preparation
|
||||
|
||||
1. Locate Unit panels and relevant keynotes
|
||||
* Bus amps
|
||||
|
||||
2. Read about the project specifications and construction type
|
||||
* Wood or Metal studs
|
||||
* Wiring Method
|
||||
* NM or MC
|
||||
* Wiring device plates
|
||||
* Decora or Standard
|
||||
* Wiring device specs
|
||||
* are 15A devices allowed?
|
||||
* Equipment (20A Kitchen and bath)
|
||||
|
||||
3. Fill out OneNote
|
||||
|
||||
### 2. Takeoff
|
||||
|
||||
1. Kitchen and Bath
|
||||
2. General assemblies
|
||||
3. Low Voltage
|
||||
4. Lighting Control
|
||||
5. Lighting Fixtures
|
||||
|
||||
Copy paste original takeoff and adjust to changes
|
||||
|
||||
### 3. Extension (Review and Checking)
|
||||
|
||||
1. Scroll through with Area selected and make sure there is takeoff for each unit type
|
||||
|
||||
## Telecom - Devices
|
||||
|
||||
### 1. Estimate preparation
|
||||
|
||||
1. Locate Proposal/Scope of Work. Determine ownership and takeoff responsibility:
|
||||
* Cabling
|
||||
* Conduit & Pathways
|
||||
* Sleeving
|
||||
2. Locate which plans the LV is taken off on
|
||||
3. Locate LV Details
|
||||
4. Read about the project specifications and construction type
|
||||
5. Fill out OneNote
|
||||
|
||||
### 2. Takeoff
|
||||
|
||||
1. Takeoff devices as shown throughout the building
|
||||
2. Takeoff Conduit Riser as needed
|
||||
|
||||
### 3. Extension (Review and Checking)
|
||||
|
||||
1. Sleeving
|
||||
|
||||
## Telecom - Riser
|
||||
|
||||
1. Service entrance conduit "Site Low Voltage Ductbank (SLVDB)"
|
||||
2. Riser throughout building
|
||||
3. Sleeving for riser
|
||||
|
||||
## Subfeeds
|
||||
|
||||
### 1. Estimate preparation
|
||||
|
||||
1. Read about the project specifications and construction type
|
||||
* Delivery Method: (Plans & Specs, Design Build, Design Assist, Preliminary Budget)
|
||||
* Deck Thickness
|
||||
* Corridor Ceiling type
|
||||
|
||||
2. In the drawings, locate:
|
||||
* Unit Panel Schedules
|
||||
* Unit Load Calculations
|
||||
* Riser Diagram
|
||||
* Subfeed schedule (if present)
|
||||
|
||||
### 2. Takeoff
|
||||
|
||||
1. Determine wiring method
|
||||
|
||||
| Construction Type | Wiring Method | Subfeed Options |
|
||||
| ----------------- | ------------- | --------------- |
|
||||
| 1,2 | MC Cable | MC, PVC, EMT |
|
||||
| 3,4,5 | NM Cable | SER, EMT |
|
||||
|
||||
%%
|
||||
TODO: Create flow chart for wiring methods.
|
||||
Some cases to mention:
|
||||
* Deck thickness (minimum 3x conduit outer diameter)
|
||||
* Renovations (may not be able to run in slab)
|
||||
%%
|
||||
|
||||
2. Route subfeeds to the Meter Centers using appropriate adder lengths
|
||||
|
||||
> [!tip]
|
||||
> Identify if and where typicals can be used
|
||||
|
||||
3. Assign material to lengths and apply Voltage drop if applicable
|
||||
|
||||
4. Pigtails and Wireway Troughs if applicable
|
||||
|
||||
### 3. Extension (Review and Checking)
|
||||
|
||||
1. Use the extension tab to determine the Correct Quantity
|
||||
|
||||
## Switchgear
|
||||
|
||||
### 1. Estimate preparation
|
||||
|
||||
1. Initial the OneNote
|
||||
2. In the drawings, locate:
|
||||
* Riser Diagrams
|
||||
* House Panels
|
||||
|
||||
### 2. Takeoff
|
||||
|
||||
1. Copy over the Temporary assemblies from "Ben -1"
|
||||
2. Build Items in Distribution:
|
||||
* Panelboards
|
||||
* Switchboards
|
||||
* Transfer SWs
|
||||
* Meter centers
|
||||
* Generator
|
||||
3. Takeoff Common Assemblies:
|
||||
* XFMRs
|
||||
* Disconnect Switches
|
||||
* Bus Duct
|
||||
4. Takeoff Items in Item Database:
|
||||
* Wireway (Trough/Gutter)
|
||||
5. Takeoff Temp Assemblies:
|
||||
* CT Cabinet
|
||||
* Meter
|
||||
* Fire Pump
|
||||
* Fire Pump Controller
|
||||
* SPD/TVSS
|
||||
|
||||
When building panelboards/switchboards,
|
||||
add terminations according to an example from the schedules.
|
||||
Do not include feeder terminations.
|
||||
|
||||
Items to Avoid:
|
||||
* Tap Boxes
|
||||
* Bus Duct
|
||||
* Vault Room
|
||||
* Anything FPL
|
||||
* Grounding
|
||||
* Elevator Room
|
||||
|
||||
### 3. Extension (Review and Checking)
|
||||
|
||||
1. Generator
|
||||
* Ensure takeoff is in the generator Area and System breakdowns
|
||||
* Put location, quantity, and type on OneNote
|
||||
|
||||
## Low Voltage
|
||||
|
||||
### 1. Estimate preparation
|
||||
|
||||
1. Locate Proposal/Scope of Work. Determine ownership and takeoff responsibility:
|
||||
* Cabling
|
||||
* Conduit & Pathways
|
||||
* Sleeving
|
||||
2. In the drawings, locate:
|
||||
* Floor plans where LV scope is shown
|
||||
* LV Details
|
||||
3. Read about the project specifications and construction type
|
||||
4. Fill out OneNote
|
||||
|
||||
### 2. Takeoff
|
||||
|
||||
1. Takeoff devices as shown throughout the building
|
||||
2. Takeoff riser conduit as needed
|
||||
|
||||
### 3. Extension (Review and Checking)
|
||||
|
||||
1. Sleeving for riser
|
||||