@@ -0,0 +1,80 @@
---
id:
aliases: []
title: "PDI Accubid Closeout: Indirect Labor"
tags:
- authorship/original
- destiny/permanent
- occupational/closeout
- status/incomplete
- type/guide
dg-publish: true
---
# PDI Accubid Closeout: Indirect Labor
> [!info]
> Note that **Hours** is used as a quantity,
> not necessarily hours.
> [!important]
> Always round _down_ when calculating duration.
> (e.g. 90% of 32 months = 28 months)
## Office Labor
> * "OVERSIGHT (EVP, RVP's, LBR MGR & OPS DIR)"
> * "PROJECT EXCUTIVE (1/12)"
> * "PROJECT MANAGER GARDEN (1/5)"
> * "PROJECT MANAGER HD (1/3)"
> * "PROJECT MANAGER LESS THAN $20M (1/2)"
> * "PROJECT MANAGER GREATER THAN $20M (1/1)"
> * "ASSISTANT PM/PROJECT ENGINEER (1/2)"
> * ~~"ASSISTANT PM/PROJECT ENGINEER (1/1)"~~
* **Hours** <- Project duration months per BPM
## Field Supervision
**Rate $** by project region.
### Superintendent
"SUPERINTENDENT ...": **Hours** <- 1
### Structural and Distribution Foremen
"STRUCTURAL FOREMAN {Region}": **Hours** <- Per Approved Labor Plan
"DISTRIBUTION FOREMAN ...":
* **Hours** <- Per Approved Labor Plan
* **Rate $** <- Match Structural Foreman
### Rough, Trim, and Other Foremen
Rename lines "ROUGH & TRIM FOREMAN ...":
* "ROUGH ..."
* "TRIM FOREMAN ..."
* Any others shown on approved labor plan
* **Hours** <- Per Approved Labor Plan
* **Rate $** <- Match Structural Foreman
### Low Voltage/Fire Alarm Foreman
> "LOW VOLTAGE/FIRE ALARM FOREMAN (1/4)"
* **Hours** <- Double months from PDI Systems Life Safety Proposal
(e.g. 2 × "16 Months @ 25%" = 8 Months)
## Escalation
~~1% per year~~ TODO
## PDI Systems Fees
> * "FIRE ALARM - Flat Fee "
> * "LOW VOLTAGE SYSTEMS - Flat Fee"
> * "DAS - Flat Fee"
For each system included in Base Bid:
* **Hours** <- 1