id:
aliases: []
title: "PDI Accubid Closeout: Subcontractors"
tags:
- authorship/original
- destiny/permanent
- occupational/closeout
- status/incomplete
- type/guide
dg-publish: true
---
# PDI Accubid Closeout: Subcontractors
> [!important]
> Subcontractor quotes ==must include tax==.
Clear **Markup %** for all lines.
## Quotes
Include all quotes from BPM.
If system is not included in the base bid,
set **Adjustment %** to -100%
### `TWO WAY COMMUNICATION`
* **Vendor** <- "PDI SYSTEMS"
* **Quote** <- Per PDI Systems proposal
* **Notes** <- Quote date
### `FIRE ALARM`
* **Vendor** <- "PDI SYSTEMS"
* **Quote** <- Per PDI Systems proposal
* **Notes** <- Quote date; # hours in quote
## Budgets
### `PDI ENGINEERING COORDINATION STUDIES`
Only if not included in switchgear quote.
### `EXCAVATION`
Only if we own primary conduit or Site Low Voltage Duct Bank:
* **Vendor** <- "PDI BUDGET"
* **Quote** <- $10,000
### `WIREWAYS | TROUGHS | PULL BOXES`
* **Vendor** <- "PDI BUDGET"
* **Quote** <- $10,000 per building (subject to adjustment)
### `FIRE STOP`
* **Vendor** <- "PDI BUDGET"
* **Quote** <- $25 per Unit (subject to adjustment)
### `RIGGING`
* **Vendor** <- "PDI BUDGET"
* **Quote** <- Sum of costs per generator:
* _less than 800kW_ = $5k each
* _800kW and larger_ = $10k each
### `FUEL`
* **Vendor** <- "PDI BUDGET"
* **Quote** <- ...
* _High Density:_ $5k
* _High Rise:_ $10k