# 2026-02-17 16:36:35
|
||||
|
||||
[[earned-value-management]]
|
||||
is frequently stated to be capable of
|
||||
"measuring project performance and progress
|
||||
_in an objective manner_",[^1]
|
||||
an analysis that is either optimistic
|
||||
or totally misleading, depending on the context.
|
||||
|
||||
[^1]: [Wikipedia](https://en.wikipedia.org/wiki/Earned_value_management) (emphasis added)
|
||||
|
||||
EVM can be an objective measure of _progress_,
|
||||
but measuring _performance_,
|
||||
variance of actual cost/hours versus estimated,
|
||||
(obviously) requires an estimate,
|
||||
which is subject to bias and error.
|
||||