@@ -0,0 +1,22 @@
---
id: 2025-07-18_estimating-isnt-engineering
aliases: []
tags: []
---
# Estimating Isn't Engineering
A peer recently expressed frustration to me
about the declining quality of construction drawings,
specifically how scope is often ~~required but not detailed~~.
%%
TODO: discussion based on the difference between engineering,
(which requires knowledge of subject matter)
and estimation
(which requires knowledge of ~~impact~~).
%%
It's not engineering to budget for the most likely case.
Estimators need not know _why_ there tends to be ~~example~~,
they need need only have basis for applying that generalization to another project.
+8 -1
View File
@@ -4,7 +4,10 @@ Standardize formatting and input methods for common
(mostly multi-family specific) (mostly multi-family specific)
project info, including: project info, including:
* level names * levels by elevation
* unit types
* info
* by level
* area types by level * area types by level
* switchgear by level * switchgear by level
* feeders * feeders
@@ -13,5 +16,9 @@ project info, including:
To calculate regular quantities To calculate regular quantities
* by feeder routing
* sleeving * sleeving
* conductor support * conductor support
* by area
* temp power
+62
View File
@@ -0,0 +1,62 @@
# Final SOE
## 1. Trash Chute
- Check elevations for floor height
- Uncheck Link 'Enable Livecount'
- CA.33(Misc. Ass.). 2
- 100' Horizontal (If not shown)
- Vertical Put in Typical
- Check Bottom of chute if taken off already in elec. THIS IS ONLY FOR THE HORIZONTAL
## 2. CU/IP
- Units Condensing Unit
- Mechanical Connection
## 3. Slab Deck
- Create Area Typical for every Concrete slab floor
- ID.37.16.1
- ID. MISC PDI PRODUCT. MISC MATERIAL. SLAB/DECK
- 2 Typicals
- 'All Building'
- 1 every level (Not Roof)
- HD 1 Per Section
- 'All Garage'
- 1 every level
## 4. Temporary Power & Lighting
```
Area = ""
```
- ID.27.
- 3/4/5 (A-bid>>)
- 8/9
- Total GSF - Garage GSF = Building Size
- Garage SF = Temp lighting Garage
- Enter in count
Gardens: Take off 1 Tpole `ID.28.1` per 150' per building
TEMP LIGHTING ^^^^
## 5. Irrigation pumps
- SYSTEM: `MISC - Site Miscellaneous`
- (3) 3Phase 30A 200' Mech. Con.
- Append to name: "Irrigation Pump - "
## 6. Lightning Protection
- Check line Item on Proposal
- Go to the notes and take off
+11
View File
@@ -0,0 +1,11 @@
# PDI Takeoff Scratch
Notes taken in review with Joel.
%% TODO: Split to more appropriate notes and delete this one. %%
* Use 15ft adders for site runs
(primaries, secondaries, etc.),
as opposed to standard 10ft adder,
to account for variability.
@@ -64,6 +64,15 @@ He later refers to the tendency to overvalue competence
in the role of achieving improbable accomplishments in the role of achieving improbable accomplishments
as the "Red Baron effect". as the "Red Baron effect".
### There's Always Enough Data
Hubbard challenges the popular rebuttal
that X industry lacks the data to use quantitative models.
> [!quote] Fallacy of Close Analogy - p.236
> ...the belief that unless two things are identical in every way,
> nothing learned from one can be applied to the other.
## Mentioned Topics and Abbreviations ## Mentioned Topics and Abbreviations
* Analytic Hierarchy Process (AHP) * Analytic Hierarchy Process (AHP)