vault backup: 2025-10-13 16:32:45

This commit is contained in:
2025-10-13 16:32:45 -04:00
parent fb5a551b6e
commit e0b34d3ab4
22 changed files with 16011 additions and 63 deletions
+20 -16
View File
@@ -2,10 +2,10 @@
id:
aliases: []
tags:
- destiny/permanent
- occupational
- status/draft
- type/guide
- destiny/permanent
- occupational
- status/draft
- type/guide
title: Pre-Takeoff Confirmation
---
# Pre-Takeoff Confirmation
@@ -24,34 +24,38 @@ and the scope included in the bid team's proposed price.
> * Drawings: GMP, 2025-09-11
> * Project Manual: GMP Specifications, 2025-09-11
> * Proposal: 2025-07-03
> * Takeoff Stage: **Full Take Off**
>
> Also, please confirm:
>
> 1. Are there any variations from the drawings that we need to include in our takeoff?
> 2. Any accepted/pending alternates?
> 3. We are currently taking off **Full Take Off**.
> 4. Feeders/Subfeeds will be per Schedule on drawings (AL +100 A).
>
> * Feeders -- PVC UG, EMT OH.
> * Subfeeds -- MC for metal stud units, SER all other units.
> * VD -- As shown for subfeeds, 2% Feeders
> Feeders:
> * Size per Schedule on drawings (AL +100 A).
> * PVC UG, EMT OH.
>
> Subfeeds:
> * MC for metal stud units, SER all other units
>
> Voltage Drop: As shown for subfeeds, 2% Feeders
>
> Units:
> * Devices -- Standard Duplex/Toggle
> * USB Rec -- As shown, plus 1 per bedroom (Type A & C).
> * Studs -- Metal in M units, Wood all other locations.
> * Telecom -- 30" UDP, CAT6. (use 28" in takeoff)
> * Smoke Det -- 120V
> * Devices: Standard Duplex/Toggle
> * USB Rec's: As shown, plus 1 per bedroom (Type A & C).
> * Studs: Metal in M units, Wood all other locations.
> * Telecom: 30" UDP, CAT6. (use 28" in takeoff)
> * Smoke Detection: 120V
>
> Fire Alarm:
> * Pathways: Free Air
> * 2Way: Included
> * 2-Way: Included
>
> Electrical:
> * Devices: Decora Amenities, Duplex/Toggle BOH
>
> Fixtures:
> * Cable: LV in Amenity Areas
> * Occupancy Sensor: Local
> * Occupancy Sensors: Local
>
> Thank you,