vault backup: 2026-04-27 17:01:41
This commit is contained in:
@@ -0,0 +1,83 @@
|
||||
---
|
||||
id: 2026-04-27T12:56:35-0400
|
||||
title: 2026-04-27 12:56:35
|
||||
tags: []
|
||||
daily: "[[2026-04-27]]"
|
||||
---
|
||||
# 2026-04-27 12:56:35
|
||||
|
||||
## Virginia Live! Internal Review
|
||||
|
||||
[[virginia-live-casino-and-hotel]]
|
||||
|
||||
Underfloor power is Reloc.
|
||||
Customer is curious if it would be more cost effective to use MC.
|
||||
|
||||
Objective is to discuss closeout mainly:
|
||||
quotes and subs.
|
||||
|
||||
FF&E
|
||||
Concern that all fixtures are captured
|
||||
|
||||
"add a line for aiming and testing"
|
||||
1 week (80 hours)
|
||||
|
||||
Shift rate
|
||||
"in the past we've paid a little more for night work,
|
||||
but nothing crazy"
|
||||
|
||||
$2,500 per day scaffold
|
||||
|
||||
### Site Services
|
||||
|
||||
Ditch witches for most excavation
|
||||
|
||||
idea floated to buy equipment rather than rent
|
||||
bobcat
|
||||
wire puller
|
||||
hydraulic bender
|
||||
|
||||
Do we own dewatering?
|
||||
pretty sure yes
|
||||
|
||||
### MV Terminations
|
||||
|
||||
No one at PDI can perform MV terms
|
||||
so they must be subbed out
|
||||
|
||||
worst case $300k
|
||||
|
||||
9 terms $60k
|
||||
|
||||
to be quoted by Ops
|
||||
|
||||
### Testing
|
||||
|
||||
primary injection testing
|
||||
|
||||
NETA testing
|
||||
|
||||
to be quoted by Ops
|
||||
|
||||
### Rigging
|
||||
|
||||
Ops quoted $85k to take one generator off the truck.
|
||||
|
||||
to be quoted by Ops
|
||||
|
||||
### Burden
|
||||
|
||||
PTO not included in burden
|
||||
because it is not charged to the job
|
||||
|
||||
### Admin Housing
|
||||
|
||||
Ops paying $4,500 for 6-bed
|
||||
|
||||
### Composite Cleanup
|
||||
|
||||
terms in contract
|
||||
|
||||
### Permits
|
||||
|
||||
to be quoted by Ops
|
||||
Reference in New Issue
Block a user