The purpose of the pre-takeoff confirmation is to address potential discrepancies between the requirements of the project documents and the scope included in the pdi-bid-estimating team's proposed price.

Procedure

Complete the Template

Complete conest-pre-takeoff-email-template for the project. Direction is included in comments.

Send the Email

Paste the completed template content to the body of a new email.

Subject: "Pre-Takeoff Confirmation - ..."

To:

  • Preconstruction Manager %% Brian %%
  • Senior Bid Estimator %% christian-pereiro %%
  • Bid Estimator or Associate Estimator (if applicable)

CC:

  • Senior Construction Estimator %% joel-jansen %%
  • ConEst Manager (josh-ford)
  • Director of Estimating (corwin-fluit)
  • Jessalyn Williams