### Belle Meade Director Review
|
|
|
|
[[estimating-director-review]] for [[belle-meade-plaza]]
|
|
lead by [[corwin-fluit]],
|
|
attended by [[joel-jansen]] and [[zane-meyers|myself]].
|
|
|
|
#### Takeoff Review
|
|
|
|
Reviewed takeoff by system.
|
|
|
|
##### Retail Village Temporary Power
|
|
|
|
Joel changed square foot budgets to temporary pole budgets only
|
|
due to minimal scope (warm shell).
|
|
|
|
##### Generator Scope
|
|
|
|
Confirmed generator quotes include furnishing docking station.
|
|
|
|
##### Feeder Lengths
|
|
|
|
Confirmed validity of longer feeder lengths:
|
|
Generator to Tower B
|
|
|
|
##### Grounding
|
|
|
|
Takeoff appears to be missing some or all grounding.
|
|
To be added if necessary.
|
|
|
|
##### Subfeed Sizing
|
|
|
|
Based on ampacity, subfeeds are oversized.
|
|
Sizing was per feeder schedule.
|
|
Takeoff approved unchanged.
|
|
|
|
##### Undercabinet Wiremold
|
|
|
|
Multi-outlet assemblies above unit kitchen countertops were not taken off,
|
|
nor was branch wiring for the same.
|
|
Joel to confirm takeoff requirement with bid.
|
|
|
|
##### Amenity Homeruns
|
|
|
|
No homeruns for amenity lighting or electrical were taken off.
|
|
Joel to add these.
|
|
|
|
> [!info] Circuits per Raceway
|
|
> Corwin stated that---assuming no overriding specification---
|
|
> up to 6 circuits per raceway are permissible.
|
|
|
|
##### Lighting Control
|
|
|
|
Lighting control takeoff was reviewed,
|
|
no changes were recommended.
|
|
|
|
> [!info] Lighting Control Pre-Work
|
|
> Corwin stated that with the imminent changes to lighting control takeoff,
|
|
> it will be necessary for estimators to more intently consider the design:
|
|
> noting quantities of lighting zones and controllers,
|
|
> even where not explicitly shown.
|
|
|
|
##### Telecom
|
|
|
|
Confirmed unit telecom requirements.
|
|
|
|
Backbone was mistakenly taken off in Telecom.
|
|
|
|
##### Retail Fire Alarm
|
|
|
|
Retail village fire alarm devices were taken off free-air,
|
|
Joel to substitute for EMT.
|
|
|
|
#### Extension Review
|
|
|
|
Reviewed extension quantities and costs.
|
|
Of particular note were:
|
|
|
|
* conduit
|
|
* wire
|
|
* cable
|
|
* wiring devices
|
|
|
|
#### Labor Plan Review
|
|
|
|
Hours per square foot was lower than expected,
|
|
this was rationalized as being due
|
|
to the relatively high portion of garage and shell retail space.
|
|
|
|
%%
|
|
"Openings per unit" was another metric considered---
|
|
higher than expected in this case---
|
|
however I didn't catch the significance of this.
|
|
%%
|