## Decomposition Fallacy
|
|
|
|
I have expressed in other notes[^1] my frustration
|
|
with how estimate decomposition is most frequently explained:
|
|
as an intuitive process which can not be performed incorrectly
|
|
and by definition creates a more accurate estimate.
|
|
|
|
[^1]: * [[2026-01-25_21-02-00]]
|
|
* [[2026-01-25_22-59-00]]
|
|
|
|
The argument that an estimate based on the aggregation of intermediate estimates
|
|
is necessarily more reliable than one made in one go
|
|
is intuitive, but a [non sequitur](https://en.wikipedia.org/wiki/Formal_fallacy).
|
|
|
|
Frequently, decomposition is explicitly _unhelpful_
|
|
due to its neglect of the [portfolio effect](https://financial-dictionary.thefreedictionary.com/portfolio+effect).
|
|
If an estimator can give a high confidence estimate
|
|
of total dollars spent on rental equipment over the life of a project,
|
|
it does not follow that they could give one for
|
|
dollars spent on scissor lifts alone with greater or even equal confidence.[^2]
|
|
|
|
[^2]: I chose this example specifically
|
|
because it has been an issue at both EC's I've estimated for.
|
|
We set a target based on some well founded model
|
|
(\$0.25 per direct labor hour or 1% of total sell price),
|
|
then 3--4 decently paid estimators spend up to an hour
|
|
discussing how to make that target
|
|
from quantities and durations of individual pieces of equipment.
|
|
Ultimately none are totally satisfied with it, nor should they be,
|
|
since the actual quantities, durations, and equipment types will be quite different,
|
|
and the entire exercise was pointless.
|
|
|
|
My criticism is not entirely fair, however.
|
|
Fermi and MacGregor's estimation problems have correct answers
|
|
and are thus a different class entirely
|
|
from those I'm most familiar with.
|
|
I choose to criticize decomposition generally despite this
|
|
because the distinction is rarely acknowledged by its advocates
|
|
so "decomposition = good" pervades the estimating zeitgeist completely,
|
|
and I get baffled, horrified, or patronizing looks when I suggest
|
|
that complete quantity takeoff may not be more accurate
|
|
than a parametric budget that could be completed in a day.
|