# 2026-04-23 10:01:40
## Virginia Live! Director Review
[[estimating-director-review]] for
[[virginia-live-casino-and-hotel]]:
## Switchgear
Note extensive emergency power provisions
verify control wiring for generator to ATS
#### Lighting HR's
count of circuits, control zones in takeoff notes
lot length
#### Temporary Power
Used two `TEMPORARY POWER - HR`
Narrative
extended light layouts
#### Generator
3000 gallons * 6 dollars per gallon = $18000
#### Labor
ASL Column 2 with adjustments
Site Labor +50%
#### Medium Voltage
Medium voltage cabling downstream of
#### Underground Runs
need rigid 90's for PVC runs 200ft and above
> horizontal? vertical? both?
#### Fixture Labor
Tape light: 1 hour per 6 feet
snap together linear: 1 hour per 5 feet
##### Center Bar Fixture
assuming each crystal is an individual fixture
over 5000 crystals
80 circuits
Arch set A-GAM-442
##### Dragon Fixture
1000 hours
#### Lighting Control
"Networked" to mean either
"Centralized"
or "Standalone" with Network Bridges.
> Wattstopper Network Bridges are limited to 64 devices (zones)
#### DAS
Sold Design Build
#### Historicals
Want to know
casino cost per square foot
#### Composite Cleanup
#### Multi-Shift Impact
20% of hours
add $5 per hour
#### Indirect Labor
16% burden
#### Facade
Extra cost for facade lighting install
250,000
"Go to 150k"