PDI Accubid Closeout: Subcontractors
Important
Subcontractor quotes ==must include tax==.
Clear Markup % for all lines.
Quotes
Include all quotes from BPM. If system is not included in the base bid, set Adjustment % to -100%
TWO WAY COMMUNICATION
- Vendor <- "PDI SYSTEMS"
- Quote <- Per PDI Systems proposal
- Notes <- Quote date
FIRE ALARM
- Vendor <- "PDI SYSTEMS"
- Quote <- Per PDI Systems proposal
- Notes <- Quote date; # hours in quote
Budgets
PDI ENGINEERING COORDINATION STUDIES
Only if not included in switchgear quote.
EXCAVATION
Only if we own primary conduit or Site Low Voltage Duct Bank:
- Vendor <- "PDI BUDGET"
- Quote <- $10,000
WIREWAYS | TROUGHS | PULL BOXES
- Vendor <- "PDI BUDGET"
- Quote <- $10,000 per building (subject to adjustment)
FIRE STOP
- Vendor <- "PDI BUDGET"
- Quote <- $25 per Unit (subject to adjustment)
RIGGING
- Vendor <- "PDI BUDGET"
- Quote <- Sum of costs per generator:
- less than 800kW = $5k each
- 800kW and larger = $10k each
FUEL
- Vendor <- "PDI BUDGET"
- Quote <- ...
- High Density: $5k
- High Rise: $10k