Virginia Live! Director Review
estimating-director-review for virginia-live-casino-and-hotel:
Switchgear
Note extensive emergency power provisions verify control wiring for generator to ATS
Lighting HR's
count of circuits, control zones in takeoff notes lot length
Temporary Power
Used two TEMPORARY POWER - HR
Narrative extended light layouts
Generator
3000 gallons * 6 dollars per gallon = $18000
Labor
ASL Column 2 with adjustments
Site Labor +50%
Medium Voltage
Medium voltage cabling downstream of
Underground Runs
need rigid 90's for PVC runs 200ft and above
horizontal? vertical? both?
Fixture Labor
Tape light: 1 hour per 6 feet
snap together linear: 1 hour per 5 feet
Center Bar Fixture
assuming each crystal is an individual fixture over 5000 crystals 80 circuits
Arch set A-GAM-442
Dragon Fixture
1000 hours
Lighting Control
"Networked" to mean either "Centralized" or "Standalone" with Network Bridges.
Wattstopper Network Bridges are limited to 64 devices (zones)
DAS
Sold Design Build
Historicals
Want to know casino cost per square foot
Composite Cleanup
Multi-Shift Impact
20% of hours add $5 per hour
Indirect Labor
16% burden
Facade
Extra cost for facade lighting install 250,000
"Go to 150k"