Virginia Live! Director Review

estimating-director-review for virginia-live-casino-and-hotel:

Switchgear

Note extensive emergency power provisions verify control wiring for generator to ATS

Lighting HR's

count of circuits, control zones in takeoff notes lot length

Temporary Power

Used two TEMPORARY POWER - HR

Narrative extended light layouts

Generator

3000 gallons * 6 dollars per gallon = $18000

Labor

ASL Column 2 with adjustments

Site Labor +50%

Medium Voltage

Medium voltage cabling downstream of

Underground Runs

need rigid 90's for PVC runs 200ft and above

horizontal? vertical? both?

Fixture Labor

Tape light: 1 hour per 6 feet

snap together linear: 1 hour per 5 feet

Center Bar Fixture

assuming each crystal is an individual fixture over 5000 crystals 80 circuits

Arch set A-GAM-442

Dragon Fixture

1000 hours

Lighting Control

"Networked" to mean either "Centralized" or "Standalone" with Network Bridges.

Wattstopper Network Bridges are limited to 64 devices (zones)

DAS

Sold Design Build

Historicals

Want to know casino cost per square foot

Composite Cleanup

Multi-Shift Impact

20% of hours add $5 per hour

Indirect Labor

16% burden

Facade

Extra cost for facade lighting install 250,000

"Go to 150k"