## Virginia Live! Director Review
|
|
|
|
[[estimating-director-review]] for
|
|
[[virginia-live-casino-and-hotel]]:
|
|
|
|
## Switchgear
|
|
|
|
Note extensive emergency power provisions
|
|
verify control wiring for generator to ATS
|
|
|
|
#### Lighting HR's
|
|
|
|
count of circuits, control zones in takeoff notes
|
|
lot length
|
|
|
|
#### Temporary Power
|
|
|
|
Used two `TEMPORARY POWER - HR`
|
|
|
|
Narrative
|
|
extended light layouts
|
|
|
|
#### Generator
|
|
|
|
3000 gallons * 6 dollars per gallon = $18000
|
|
|
|
#### Labor
|
|
|
|
ASL Column 2 with adjustments
|
|
|
|
Site Labor +50%
|
|
|
|
#### Medium Voltage
|
|
|
|
Medium voltage cabling downstream of
|
|
|
|
#### Underground Runs
|
|
|
|
need rigid 90's for PVC runs 200ft and above
|
|
|
|
> horizontal? vertical? both?
|
|
|
|
#### Fixture Labor
|
|
|
|
Tape light: 1 hour per 6 feet
|
|
|
|
snap together linear: 1 hour per 5 feet
|
|
|
|
##### Center Bar Fixture
|
|
|
|
assuming each crystal is an individual fixture
|
|
over 5000 crystals
|
|
80 circuits
|
|
|
|
Arch set A-GAM-442
|
|
|
|
##### Dragon Fixture
|
|
|
|
1000 hours
|
|
|
|
#### Lighting Control
|
|
|
|
"Networked" to mean either
|
|
"Centralized"
|
|
or "Standalone" with Network Bridges.
|
|
|
|
> Wattstopper Network Bridges are limited to 64 devices (zones)
|
|
|
|
#### DAS
|
|
|
|
Sold Design Build
|
|
|
|
#### Historicals
|
|
|
|
Want to know
|
|
casino cost per square foot
|
|
|
|
#### Composite Cleanup
|
|
|
|
#### Multi-Shift Impact
|
|
|
|
20% of hours
|
|
add $5 per hour
|
|
|
|
#### Indirect Labor
|
|
|
|
16% burden
|
|
|
|
#### Facade
|
|
|
|
Extra cost for facade lighting install
|
|
250,000
|
|
|
|
"Go to 150k"
|