id, aliases, tags
Low Voltage
Sequence
1. Estimate preparation
Telecom - Riser
- Service entrance conduit "Site Low Voltage Ductbank (SLVDB)"
- Riser throughout building
- Sleeving for riser
Telecom - Devices
- Locate Proposal/Scope of Work. Determine ownership and takeoff responsibility:
- Cabling
- Conduit & Pathways
- Sleeving
- Locate which plans the LV is taken off on
- Locate LV Details
- Read about the project specifications and construction type
- Fill out OneNote
2. Takeoff
- Takeoff devices as shown throughout the building
- Takeoff Conduit Riser as needed
3. Extension (Review and Checking)
- Sleeving
Low Voltage
1. Estimate preparation
- Locate Proposal/Scope of Work. Determine ownership and takeoff responsibility:
- Cabling
- Conduit & Pathways
- Sleeving
- In the drawings, locate:
- Floor plans where LV scope is shown
- LV Details
- Read about the project specifications and construction type
- Fill out OneNote
2. Takeoff
- Takeoff devices as shown throughout the building
- Takeoff riser conduit as needed
3. Extension (Review and Checking)
- Sleeving for riser