# Award Analysis
|
|
|
|
BPM > Reports > Awards
|
|
The HUB > HUB Insights > WIGs, KPIs & milestones
|
|
|
|
Inception to Date (ITD)
|
|
|
|
$$
|
|
"Overrun $" = "ITD Cost $" - "Baseline Cost $"
|
|
|
|
"Overrun %" = "Overrun $" / "Baseline Cost $"
|
|
|
|
"Overrun %" = "ITD Cost $" / "Baseline Cost $" - 1
|
|
$$
|
|
|
|
> [!observation]
|
|
> Curiously, we've decreased expected uncertainty significantly,
|
|
> but are consistently overbidding by ~13%.
|
|
|
|
This observation is likely due to more recent projects still being in their infancy,
|
|
where costs have not been totally realized.
|