## Sequence
|
|
|
|
### 1. Estimate preparation
|
|
|
|
1. Initial the OneNote
|
|
2. In the drawings, locate:
|
|
* Riser Diagrams
|
|
* House Panels
|
|
3. Copy over default Temporary Assemblies from ?
|
|
|
|
### 2. Takeoff
|
|
|
|
1. Build Items in Distribution:
|
|
* Panelboards
|
|
* Switchboards
|
|
* Meter centers
|
|
* Generators
|
|
* Transfer switches
|
|
* Generator connection cabinets
|
|
|
|
2. Takeoff Common Assemblies:
|
|
* XFMRs
|
|
* Disconnect switches
|
|
|
|
3. Takeoff Items in Item Database:
|
|
* Wireway (Trough/Gutter)
|
|
|
|
4. Takeoff Temp Assemblies:
|
|
* CT Cabinet
|
|
* Meter
|
|
* Fire Pump
|
|
* Fire Pump Controller
|
|
* SPD/TVSS
|
|
|
|
When building panelboards/switchboards,
|
|
add terminations according to an example from the schedules.
|
|
**Do not include feeder terminations.**
|
|
|
|
Items to Avoid:
|
|
* Tap Boxes
|
|
* Bus Duct
|
|
* Vault Room
|
|
* Anything FPL
|
|
* Grounding
|
|
* Elevator Room
|
|
|
|
#### Enclosed Circuit Breakers
|
|
|
|
Treat as disconnect switch.
|
|
|
|
#### Generators
|
|
|
|
Add `GENERATOR SET UP`
|
|
|
|
#### Generator Connection Cabinets
|
|
|
|
Use a Distribution Panel of equal amps.
|
|
|
|
#### Transfer Switches
|
|
|
|
> "300A ATS"
|
|
|
|
##### Transfer Switches 1200A+
|
|
|
|
Use 1200A MTS/ATS, and add:
|
|
|
|
- ==CA.33.14.AMPS==
|
|
- Factor 1 = 3
|
|
- ==Delete 1200A==
|
|
|
|
#### Meter Centers
|
|
|
|
`SWITCHGEAR & METER CENTERS`/`METER CENTERS`/`... METERING SECTION`
|
|
|
|
Adjust Factor 1 for meter stacks, delete zeroed items.
|
|
|
|
### 3. Extension (Review and Checking)
|
|
|
|
1. Generator
|
|
* Ensure takeoff is in the generator Area and System breakdowns
|
|
* Put location, quantity, and type on OneNote
|