title: Wiring Method Selection
|
|
dg-publish: true
|
|
---
|
|
# Wiring Method Selection
|
|
|
|
Determine where each wiring method can be used.
|
|
|
|
> [!important]
|
|
> This note covers general, system-agnostic selection.
|
|
> For certain specific applications,
|
|
> It may be necessary to deviate from the general case.
|
|
|
|
%% TODO
|
|
Scripts by others tend to beg questions of edge cases.
|
|
It's my intent that if a rule holds in _all_ cases,
|
|
even the super special one you're thinking I didn't consider,
|
|
that I specifically say so.
|
|
If I didn't say so, and your edge case is not covered,
|
|
you should seek clarification.
|
|
%%
|
|
|
|
## Example Wiring Method Selection
|
|
|
|
Below is an example Wiring Method Selection
|
|
for a [[ibc-construction-types#^5-over-1|podium]] construction.
|
|
|
|
> [!example]
|
|
> Wire Material:
|
|
> * Less than 100A: CU
|
|
> * 100A and larger: AL
|
|
>
|
|
> Outdoors:
|
|
> * Above-ground: EMT-Comp
|
|
> * Underground: PVC w/ Rigid Elbows
|
|
>
|
|
> Levels 1-2 (Type IA):
|
|
> * Concealed: MC
|
|
> * Exposed to Structure:
|
|
> * Up to 2"C: PVC In-Slab
|
|
> * 2-1/2"C and larger: EMT-SS OH
|
|
>
|
|
> Levels 3-5 (Type IIIA):
|
|
> * Concealed: NM/SER
|
|
> * Exposed to Structure: PVC OH
|
|
|
|
%%
|
|
This needs reworking.
|
|
I know PVC is preferable to MC in the case of feeders, subfeeds, and possibly home runs,
|
|
but I think they swap for branch.
|
|
%%
|
|
|
|
## Standard Indoor Wiring Methods
|
|
|
|
NM/SER < PVC in Slab < MC < EMT-SS < EMT-Comp
|
|
|
|
### NM/SER Overhead
|
|
|
|
Nonmetallic-sheathed cables are combustible,
|
|
so not permissible in Type [[ibc-construction-types#Type I Fire Resistive Non-Combustible|I]],
|
|
[[ibc-construction-types#Type II Non-Combustible|II]] constructions.
|
|
|
|
#### Concealment
|
|
|
|
Cable type wiring methods (MC, NM, SE)
|
|
may only be used where they will be concealed from view.
|
|
|
|
### PVC In-Slab
|
|
|
|
May require rigid stub-ups in certain cases,
|
|
which could make EMT more cost-effective.
|
|
Consult with the Senior Construction Estimator in this case.
|
|
|
|
> [!important]
|
|
> Be careful of ambiguous terminology in specifications and PDI proposals:
|
|
> "underground" and "below grade" are sometimes used inappropriately
|
|
> to describe PVC in-slab.
|
|
> It may be that rigid stub-ups are only necessary when emerging from grade (dirt),
|
|
> but not when emerging from the slab.
|
|
|
|
#### Garage Slab
|
|
|
|
_Conventional Slab_: PVC in Slab
|
|
_Precast_: EMT
|
|
|
|
See [[pdi-breakdowns#Garage]] for more info.
|
|
|
|
#### Slab Thickness
|
|
|
|
Conduits may only be routed through slabs of thickness
|
|
at least 3 times the outer diameter of the conduit.
|
|
|
|
| Conduit Size | Minimum Slab Thickness (in) |
|
|
| ------------:| ---------------------------:|
|
|
| 1/2" | 3.0 |
|
|
| 3/4" | 3.5 |
|
|
| 1" | 4.0 |
|
|
| 1-1/4" | 5.0 |
|
|
| 1-1/2" | 6.0 |
|
|
| 2" | 7.5 |
|
|
| 3" | 9.0 |
|
|
| 2-1/2" | 10.5 |
|
|
| 3-1/2" | 12.0 |
|
|
| 4" | 13.5 |
|
|
| 5" | 17.0 |
|
|
| 6" | 20.0 |
|
|
|
|
#### Shear Walls
|
|
|
|
[[construction-methods#Shear Walls|Shear Walls]]
|
|
|
|
Shear walls, like those around stairwells and elevator shafts,
|
|
may be routed through with special permission.
|
|
|
|
#### Post-Tensioned Slabs
|
|
|
|
[[construction-methods#Post-Tensioned Slab|Post-Tensioned Slab]]
|
|
|
|
> [!cite] [[joel-jansen]] 2025-08-15, in reference to [[belle-meade-plaza|Belle Meade Plaza]] (pp.)
|
|
> No affect on takeoff. Routing in slab still possible.
|
|
|
|
> [!cite] [[joel-jansen]] 2025-08-21, in reference to [[belle-meade-plaza|Belle Meade Plaza]] (pp.)
|
|
> PT slabs do have some affect on takeoff.
|
|
> 3in conduit can not be run in an 11in PT slab.
|
|
|
|
#### Pan Deck Slabs
|
|
|
|
[[construction-methods#Pan Deck Slab|Pan Deck Slab]]
|
|
|
|
> [!cite] [[joel-jansen]] 2025-08-15, in reference to [[belle-meade-plaza|Belle Meade Plaza]] (pp.)
|
|
> Do not route in slab.
|
|
|
|
### MC Cable Overhead
|
|
|
|
_Market Type = Assisted Living:_ MC-AP may be required.
|
|
|
|
#### Concealment
|
|
|
|
Cable type wiring methods (MC, NM, SE)
|
|
may only be used where they will be concealed from view.
|
|
|
|
> [!important] Exception:
|
|
> Temporary provisions for unfinished spaces
|
|
> (e.g. core and shell [[pdi-building-types#Retail|retail]])
|
|
|
|
#### Multi-Circuit Homeruns
|
|
|
|
Different schools of thought exist
|
|
on whether to use multi-neutral MC or EMT for homeruns.
|
|
Which is more cost-effective
|
|
is apparently subject to transient market conditions.
|
|
Seek clarification from your senior on a job by job basis.
|
|
|
|
> [!quote] Art Baldwin (pp.)
|
|
> Multi-circuit MC is not cost-effective
|
|
> when considering the difficulty of rework.
|
|
> Use conduit, even EMT if necessary.
|
|
|
|
### EMT Overhead
|
|
|
|
Set-screw fittings are cheaper than compression,
|
|
but may not be acceptable.
|
|
|
|
> [!info]
|
|
> EMT has a third coupling type "indenter",
|
|
> which are crimped onto the conduit using a special tool.
|
|
> These are usually only mentioned in specifications
|
|
> to say that they are unacceptable.
|
|
|
|
[[2025-10-15_09-32-00#Vanderbilt Central Neighborhood Residential College Spec Interpretation]]
|
|
|
|
## Standard Outdoor Wiring Methods
|
|
|
|
PVC Underground < EMT-Comp < IMC
|
|
|
|
### PVC Underground
|
|
|
|
May require rigid stub-ups.
|
|
|
|
### EMT Overhead
|
|
|
|
Use compression fittings.
|
|
|
|
## Nonstandard Indoor Wiring Methods
|
|
|
|
### PVC Overhead
|
|
|
|
Not usually permissible, except in Florida.
|
|
|
|
## By Specification
|
|
|
|
> [!info] Example Specs Relevant to Wiring Methods Selection
|
|
> * 26XXXX - Raceway And Boxes For Electrical Systems
|
|
> * 26XXXX - Conduits For Electrical Systems
|
|
> * 26XXXX - Underground Ducts And Raceways For Electrical Systems
|
|
>
|
|
> * 26XXXX - Low-Voltage Electrical Power Conductors And Cables
|
|
>
|
|
> * 26XXXX - General Requirements For Electrical
|
|
> * 26XXXX - Common Work Results For Electrical
|
|
|
|
## Flow Chart
|
|
|
|
```mermaid
|
|
flowchart
|
|
A[Construction Type]
|
|
A -- I, II --> B[Can be run in slab?]
|
|
B -- No --> D[Concealed?]
|
|
B -- Yes --> PVC
|
|
D -- No --> EMT
|
|
D -- Yes --> MC
|
|
A -- III, IV, V --> C[Concealed?]
|
|
C -- No --> PVC
|
|
C -- Yes --> NM/SER
|
|
```
|
|
|
|
#### Fire Rated Feeders
|
|
|
|
[[fire-resistive-wiring-methods-takeoff]]
|
|
|
|
PDI estimating practice is to run all "emergency" feeds
|
|
(life-safety or just standby)
|
|
in a 2-hour rated assembly.
|
|
This usually requires no change to takeoff for high-rises
|
|
since electrical riser rooms are themselves fire-rated.
|
|
|
|
* RHW-2 insulated conductors in conduit --- "Lifeline Cable"
|
|
* 2-hour rated metal clad cable --- "Vitalink"
|