id, aliases, title, tags, daily, date-created, dg-publish, monthly, quarterly, weekly, yearly
id aliases title tags daily date-created dg-publish monthly quarterly weekly yearly
2026-03-09T15:50:49-04:00
2026-03-09 15:50:49
authorship/original
destiny/permanent
status/draft
type/timestamped
2026-03-09 2026-03-09T15:50:49-04:00 true 2026-03 2026-Q1 2026-W11 2026

2026-03-09 15:50:49

%% Implementation of conest-pre-takeoff-email-template %%

Hello Team,

Below is a comprehensive list of means & methods for Charlotte South End Hotel. Please confirm you have received this email and respond with any questions or comments.

  • Delivery Method: Plans & Specs
  • Document Stage: Issue for Permit
  • Drawings Date: 2026-02-27
  • Project Manual Date: 2026-02-27
  • Proposal Date: 2025-12-12
  • Takeoff Request Stage: Full Takeoff

Project Specification Callouts

  • Conduit: %% GRC, coupling specs, etc. %%

  • Wire:

    • Material: Aluminum 100A and larger ---E021 "ALUMINUM FEEDER SCHEDULE" Note 1(b)
    • Acceptable Manufacturers: ---Spec 260510-2 (p. 2224)
      • Encore Wire
      • General Cable
      • Okonite
      • Paranite
      • Pirelli
      • Senator
      • Southwire
  • MC Cable:

    • Application: Concealed feeders and branch circuits ---Spec XXXXXX (p. XXXX) %% Branch homeruns only; Not permitted %%
    • Acceptable Manufacturers: ---Spec 260510-2 (p. 2224)
      • Alflex
      • AFC
      • America Metal Moulding
      • Encore Wire
      • Southwire
    • ==Conductors: Copper ---Spec XXXXXX (p. XXXX)==
    • ==Armor: Steel ---Spec XXXXXX (p. XXXX)==
    • ==Jacket: PVC ---Spec XXXXXX (p. XXXX)==
  • Steel Box Depth:

    • Telecom: 2-1/8" ---Spec XXXXXX (p. XXXX)
    • Security: 2-1/8" ---Spec XXXXXX (p. XXXX)
    • Other Applications: Not specified %% 1-1/2", 2-1/8" %%
  • Floor Boxes: Sheet metal with brass or aluminum covers ---Spec XXXXXX (p. XXXX)

  • Wiring Devices:

    • Units:
      • Current rating: Unspecified. Assuming 15A for takeoff.
      • Standard/Decora: Unspecified. Assuming Toggle/Duplex for takeoff. %% 15A Decora %%
    • BOH/Common Areas:
      • Current rating: Unspecified. Assuming 20A for takeoff.
      • Standard/Decora: Unspecified. Assuming Toggle/Duplex for takeoff. %% 20A Toggle/Duplex %%
  • Switchboards:

    • Acceptable Manufacturers: ---Spec XXXXXX (p. XXXX)
      • ???
    • Bus Material: ??? ---Spec XXXXXX (p. XXXX)
    • Interrupting Current Rating: ???
  • Distribution Panelboards:

    • Acceptable Manufacturers: ---Spec XXXXXX (p. XXXX)
      • ???
    • Bus Material: ??? ---Spec XXXXXX (p. XXXX)
    • Breaker Types: ??? ---Spec XXXXXX (p. XXXX) %% Snap-on, bolt on %%
    • Interrupting Current Rating: ???
  • Load Centers:

    • Acceptable Manufacturers: ---Spec XXXXXX (p. XXXX)
      • ???
    • Bus Material: ??? ---Spec XXXXXX (p. XXXX)
    • Breaker Types: ??? ---Spec XXXXXX (p. XXXX) %% Snap-on, bolt on %%
    • Interrupting Current Rating: ???
  • Transformers:

    • Winding Material: ??? ---Spec XXXXXX (p. XXXX)
    • K-Rating: ??? %% Windings AL or CU, K-rating %%
  • Generator: (1) 500kW Diesel

    • Enclosure Specs: ??? ---Dwg. E014
    • Remote Tank: ???
    • Tank Size: ??? ---Spec XXXXXX (p. XXXX)
    • Load Banks: ??? ---Spec XXXXXX (p. XXXX)
    • Acceptable Manufacturers: ---Spec 263213-3 (p. 2323)
      • Caterpillar Tractor Co.
      • Cummins/Power Generation
      • Kohler Power Systems (MTU Engine Only)
      • MTU On-Site Energy

Project Drawing/Detail Callouts

  • Describe conflicts between drawings / proposal: %% "Plans show CU feeders, proposal calls for aluminum", Specification grade devices, etc. %%

  • Cost drivers in details not shown elsewhere on plans:

PDI System Execution Plan

  • Primaries: %% Installation only, (9) 6" PVC %%

  • Secondaries: * %% PVC UG, GRC Stub-ups, AL %%

  • Feeders: PVC UG, EMT OH; Size and material per E05-10 schedule ==(Transformer primaries and secondaries all copper)== %% PVC UG, EMT OH, AL over 100A, 2% VD %% %% Emergency Feeds MI Cable %%

  • Unit Subfeeds: ??? %% MC OH AL, VD per Chart on E5.01 %%

  • Units:

    • ??? %% 15A Decora, Disposals, T-stat, Floor Boxes, Shade Control, Doorbells, Dimmer Switches, etc. %%
  • Telecom:

    • ??? %% 42" MSDE, No Cable Homeruns, (1) 1" Back to IDF, CAT6 with Stub-ups %%
  • EV Chargers: ??? %% (42) Conduit only, (56) Conduit & Wire, (20) Conduit, Wire & Equipment %%

  • Fire Alarm: ??? %% Free-air where allowed by code. EMT Risers. %%

  • DAS: ??? %% Conduit only, Per PDI DAS Design %%

  • Low Voltage: Free-air where allowed by code. %% Free-air where allowed by code. Stub-ups to accessible ceilings. %%

Lighting Control

  • Basis of Takeoff: ??? ---??? %% Code Minimum per Energy Code Assigned, P&S, PDI Design %%

  • Area: ---Dwg. E06-01 "LIGHTING CONTROL NARRATIVE" * %% Assign Method to Areas: Line Voltage, Low-Voltage Stand Alone or Centralized System %%

Tasks/Quotes Needed for WBS

%% Delete any completed %%

  • Electrical Constructability Review
  • Electrical VDC
  • Coordination Study
  • DAS Public Safety Raceway Design