%% Implementation of [[conest-pre-takeoff-email-template]] %%
Hello Team,
Below is a comprehensive list of means & methods for Charlotte South End Hotel.
Please confirm you have received this email and respond with any questions or comments.
* **Delivery Method:** Plans & Specs
* **Document Stage:** Issue for Permit
* **Drawings Date:** 2026-02-27
* **Project Manual Date:** 2026-02-27
* **Proposal Date:** 2025-12-12
* **Takeoff Request Stage:** Full Takeoff
### Project Specification Callouts
* **Conduit:**
* EMT Fittings: _---Spec 260510 2.4(N)(2) (p. 2226)_
* Smaller than trade size 2-1/2": Compression
* Trade size 2-1/2" and larger: Set-screw
* **Wire:**
* Material: Aluminum 1 AWG and larger _---Spec 260510 2.2(C)(1) (p. 2224)_
* Acceptable Manufacturers: _---Spec 260510 2.2(D) (p. 2224)_
* Encore Wire
* General Cable
* Okonite
* Paranite
* Pirelli
* Senator
* Southwire
* **MC Cable:**
* Application: "dry locations only where approved by code authority."
_---Spec 260510 2.4(N)(8) (p. 2227)_
* Acceptable Manufacturers: _---Spec 260510 2.2(E) (p. 2224)_
* Alflex
* AFC
* America Metal Moulding
* Encore Wire
* Southwire
* **Steel Box Depth:** Not specified _---Spec 260510 2.12(A) (p. 2231)_
* **Floor Boxes:** _---Spec 260510 2.12(E) (p. 2231)_
* Box Material:
* Slab on grade: Cast iron
* Slabs above grade: Stamped steel
* Cover Material: Not specified.
* **Wiring Devices:**
* All Areas:
* Current rating: 20A _---Spec 260510 2.16(B)(1) (p. 2231)_
* Standard/Decora: Decora _---Spec 260510 2.16(D) (p. 2231)_
* **Switchboards:**
* Bus Material: "aluminum or copper, tin or silver plated" _---Spec 262000 2.6(C)(4) (p. 2297)_
* OCPD Interrupting Current Ratings: Not specified.
* Acceptable Manufacturers: _---Spec 262000 2.17(C) (p. 2307)_
* Eaton
* ABB/GE
* Schneider Electric
* Siemens
* **Panelboards:**
* Bus Material: "silver plated copper or electro-tin plated aluminum"
_---Spec 262000 2.8(E) (p. 2303)_
* Breaker Types: Bolt-on _---Spec 262000 2.9(C) (p. 2303)_
* OCPD Interrupting Current Ratings:
* Distribution Panelboards: Not specified.
* Lighting and Appliance Panelboards: Not less than 10kAIC
_---Spec 262000 2.10(A)(3) (p. 2304)_
* Acceptable Manufacturers: _---Spec 262000 2.17(C) (p. 2307)_
* Eaton
* ABB/GE
* Schneider Electric
* Siemens
* **Transformers:**
* Winding Material:
"Transformer windings shall be manufacturer's standard design,
copper or aluminum conductor. Bussing shall be copper."
_---Spec 262002.5(L) (p. 2296)_
* K-Rating: Only as shown (None shown)
_---Spec 262002.5(K) (p. 2295)_
* Acceptable Manufacturers: _---Spec 262000 2.17(D) (p. 2307)_
* Eaton
* ABB/GE
* Heavy Duty
* MGM
* Siemens
* Schneider Electric
* United Power Corp
* **Generator:** (1) 500kW Diesel _---Dwg. E05-12_
* Enclosure Specs: Not specified.
* Remote Tank: None shown or specified.
* Tank Size: 12hrs at full load _---Spec 263213 2.7(C) (p. 2326)_
* Load Banks: None shown or specified.
* Acceptable Manufacturers: _---Spec 263213 2.1(A) (p. 2323)_
* Caterpillar Tractor Co.
* Cummins/Power Generation
* Kohler Power Systems (MTU Engine Only)
* MTU On-Site Energy
### Project Drawing/Detail Callouts
* Describe conflicts between drawings / proposal:
%% "Plans show CU feeders, proposal calls for aluminum", Specification grade devices, etc. %%
* Cost drivers in details not shown elsewhere on plans:
### PDI System Execution Plan
* **Primaries:** Wiring only, duct bank by others.
* **Secondaries:** Aluminum bus duct. _---Spec 262000 2.11(D) (p. 2305)_
%% PVC UG, GRC Stub-ups, AL %%
* **Feeders:**
PVC UG, EMT OH;
Size and material per E05-10 schedule
==(AL 100A and larger,==
==transformer primaries and secondaries all copper)==
%% PVC UG, EMT OH, AL over 100A, 2% VD %%
%% Emergency Feeds MI Cable %%
* **Unit Subfeeds:** #12 Multi-Circuit MC OH (alternate for voltage drop)
%% MC OH AL, VD per Chart on E5.01 %%
%% [[2026-03-10_13-51-32#Voltage Drop]] %%
* **==Units==:**
* VFCU HVAC
* 20A Decora Switches
* 20A Decora Receptacles
%% 15A Decora, Disposals, T-stat, Floor Boxes, Shade Control, Doorbells, Dimmer Switches, etc. %%
* **Telecom:** Rough-in only
* ???
%% 42" MSDE, No Cable Homeruns, (1) 1" Back to IDF, CAT6 with Stub-ups %%
* **EV Chargers:** ???
%% (42) Conduit only, (56) Conduit & Wire, (20) Conduit, Wire & Equipment %%
* **Fire Alarm:** ???
%% Free-air where allowed by code. EMT Risers. %%
* **DAS:** ???
%% Conduit only, Per PDI DAS Design %%
* **Low Voltage:** Free-air where allowed by code.
%% Free-air where allowed by code. Stub-ups to accessible ceilings. %%
### Lighting Control
* **Basis of Takeoff:** Central dimming system per P&S, PDR quote.
* **Area:** _---Dwg. E06-01 "LIGHTING CONTROL NARRATIVE"_
* Units: Master Switch, Digital Standalone Control, 0-10V dimming.
* Amenity: Digital Central Control, 0-10V dimming
* Garage: Integral dimming occupancy sensors, 120V wiring only.
%% Assign Method to Areas: Line Voltage, Low-Voltage Stand Alone or Centralized System %%
### Tasks/Quotes Needed for WBS
%% Delete any completed %%
%%
* Electrical Constructability Review
* Electrical VDC
* Coordination Study
* DAS Public Safety Raceway Design
%%
<!--
DAS Public Safety Raceway Design is necessary
if we own DAS pathways but not the system,
since if we own the system,
the raceway design will be included in the Systems quote.
-->
Thank you,