# 2026-03-05 13:42:50
## Labor Plan
Anova
### PDI SORT CODES
| Code | Description |
| ---- | ------------------------- |
| 100 | Slab Deck |
| 200 | Rough |
| 250 | Rough (Fire alarm trough) |
| 300 | Trim |
| 400 | Wire and Cable |
| 500 | Fixtures |
| 600 | Distribution |
### Garage Slab/Deck
"PDI Sort Code, Bid Item, Phase"
### Building Slab/Deck
"PDI Sort Code, Bid Item, Phase"
Common Areas = Total
Slab & Deck Labor
Calculate Factor and apply to column **Slab-Deck**
| |
| --------------- |
| BLDG - CORRIDOR |
| BLDG - BOH |
| UNITS |
| SUBFEEDS |
| FIRE ALARM |
| AMENITY |
| RETAIL |
| OFFICE |
| KITCHEN |
| FACADE |
| GARAGE |
### Garage, Other than 100: Slab/Deck
"Phase, PDI Sort Code"
Drill into "Garage"
Total Labor Hrs of all codes other than 100.
Garage = Total \
^ Garage (rough, trim, fix, f/a, ect..) \
**Total Hours**
Calculate Factor and apply to all columns other than **Slab-Deck**
### Units
Electrical Rough (Elec. 200, 400 & 600)