Files
zmVault/2026-01-07.md
T

112 lines
3.7 KiB
Markdown

---
id:
aliases: []
title: 2026-01-07
tags:
- authorship/original
- destiny/permanent
- status/draft
- type/daily
---
# 2026-01-07
## 2026-01-07 10:03
At Ace, "residential" always meant single-family/duplex construction,
but I think now we were the outliers.
## 2026-01-07 10:05
See [[pdi-breakdowns#Location]].
I have---for some time now---
been trying to figure out the purpose of the non-system breakdowns.
[[location-vs-scope]]
Perhaps there is another dichotomy
in that an estimator may use the area classifications of the design
or according to their own understanding of each term.
For lack of a better example,
whether a "101 - KITCHEN", without provisions for cooking,
would be broken down under "Kitchen".
## 2026-01-07 10:42
When I got to work today Art admonished a fellow estimator
for not uploading _all_ of a project's drawings,
even those they did not intend to take off, to Trimble Connect.
Art suggested that the estimator should upload all the drawings,
but only add them to LiveCount as needed.
I take issue with the suggestion on principle
since doing so would not benefit the estimator or their senior
(if they aren't added, the estimator can do nothing with them),
but would require not-insignificant effort.
Effort that would ultimately benefit no one:---
Trimble Connect's ham-fisted approach to version control
means that the fewer times it must be used, the better.
> I'm currently dealing with the headache of an estimate
> where such caution was not applied.
The probability that any construction will be performed
according the drawings that we take off
(or even their immediate successors)
I suspect is slim to zero.
That Ops would have the patience to add the revisions,
fighting with Trimble Connect as they would be,
I suspect is even less.
> On my current project, after trying in vain to play by Trimble's rules,
> I started by deleting all the drawings I could
> (those without takeoff associated with them)
> then reuploaded the revised set.
> I'm confident that this would be the dominant strategy.
***
It's curious to me that the possibility of scope revisions
doesn't seem to be at the front of every estimator's mind
when doing takeoff or considering process changes,
like it was for my mentors and peers at Ace.
## 2026-01-07 12:13
#occupational #topic/estimating #topic/organization
Just now Jorge admonished another peer
for using insulated wire for pool bonding,
his rational was flawed beyond saving
(something about the difference between bonding and grounding),
but stemmed from a frustratingly common misunderstanding
that our Accubid assemblies are intended to be an accurate list
of the material to be installed.
They are not.
If they were intended to be accurate,
there would need to be several times as many.
They are a compromise between accuracy and estimator effort.
It should be assumed that for common scope,
at least one assembly should be acceptable as-is.
Pool bonding is required for at least a quarter of our jobs.
We have no bonding assemblies with bare wire.
Therefore it must be assumed that it was determined
that it would be acceptable to represent bare wire bonding with insulated wire items,
because otherwise it would be necessary to have double the assemblies,
or to ec
## 2026-01-07 16:03
#occupational #topic/estimating #topic/organization
There is a palpable animosity for [[pdi-estimating#Bid Estimating|Bid]]
in [[pdi-estimating#Construction Estimating (ConEst)|ConEst]],
stemming---I believe---from an lack of buy-in on Bid's part.
Their lack is easily explained by their [[estimating-culture#Incentives|incentive structure]]:
Since throughput is systematically prioritized over accuracy,
ConEst has a strictly antagonistic role
because it slows down the bid process.