Lighting Takeoff

Fixtures

Fixture Labor

Fixture Type Labor
Paddle Fan 1.5 hrs/ea
Pendant 1-4 hrs/ea1
Strip/Cove 0.083 hrs/ft
Site Poles 1.5 hrs/ea
Festoon 2 hrs/ea
All Others 1 hrs/ea

Fixture Branch Length

Case Standard Length
Site/Courtyard 50ft1
Garage 50ft
BOH 40ft
Corridors 40ft
Interior Amenity 40ft2
Office/Retail 50ft
Exterior Amenity 50ft
Units 20ft

Fixture Branch Wire size

Case Wire Size
Site/Courtyard #101
Garage #10
NM Cable #142
All Others #12

Garage

Fixtures

Use ENT Assembly unless spec requires otherwise.

PVC/ENT ASSEMBLIES/GARAGE FIXTURE ENT W/#10 - STEEL OCT RING PVC/ENT ASSEMBLIES/GARAGE FIXTURE W/T ROD ENT W/#10 - STEEL OCT RING

If PVC, use following assemblies:

Case Assembly Path
Ceiling PVC/ENT ASSEMBLIES/... - SLAB BOX / 45 DEG STUBBY
Wall PVC/ENT ASSEMBLIES/... - STL BOX & TILE RING / 45 DEG STUBBY/ ENT DROP

Homeruns

System = "EL - Electrical"

Use 1 Homerun for every 3 circuits in Garage

Use assembly Common Assemblies/Device Homeruns in Slab/Deck

Surface Mount

  • Wall Mount (Sconce)
  • Pendant
  • Linear
  • Tape
  • Track

| Wiring Method | Assembly Path | | ---------------------------------------------------------------------------- | | NM Cable | NM ASSEMBLIES/RND BOX BAR HNGR... | | MC Cable | MC ASSEMBLIES/SQ BOX, ROUND P RING & MNTG BRKT... | | PVC in Ceiling | PVC/ENT ASSEMBLIES/... - SLAB BOX / 45 DEG STUBBY | | PVC in Wall | PVC/ENT ASSEMBLIES/3/4" PVC W/ 3#12 - STL BOX/TILE RING | | EMT | EMT ASSEMBLIES/... - SQ BOX & ROUND P RING |

Note

Use lighting control cable assemblies in Amenity areas

Tape Lighting

Also called "cove" or "strip", however those terms are less specific and potentially confusing.

Use item FIXTURE LABOR 1/2HR and change Fct 1 to match the calculated labor.

Note

Tape lighting length is limited by the "max power length" of the model (usually measured in millimeters). Max power length is usually 5000 to 15000 mm (about 16 to 49 ft) depending on luminous output and voltage.

Separate these fixtures by labor, not length

A - Tape 0.5hr (1-6ft) - MC #12 40ft
A - Tape 1.0hr (7-12ft) - MC #12 40ft
A - Tape 1.5hr (13-18ft) - MC #12 40ft
A - Tape 2.0hr (19-24ft) - MC #12 40ft
A - Tape 2.5hr (25-30ft) - MC #12 40ft
A - Tape 3.0hr (31-36ft) - MC #12 40ft
A - Tape 3.5hr (37-42ft) - MC #12 40ft
A - Tape 4.0hr (43-48ft) - MC #12 40ft
A - Tape 4.5hr (49-54ft) - MC #12 40ft
A - Tape 5.0hr (55-60ft) - MC #12 40ft
A - Tape 5.5hr (61-66ft) - MC #12 40ft
A - Tape 6.0hr (67-72ft) - MC #12 40ft
A - Tape 6.5hr (73-78ft) - MC #12 40ft
A - Tape 7.0hr (79-84ft) - MC #12 40ft
A - Tape 7.5hr (85-90ft) - MC #12 40ft
A - Tape 8.0hr (91-96ft) - MC #12 40ft
A - Tape 8.5hr (97-102ft) - MC #12 40ft
A - Tape 9.0hr (103-108ft) - MC #12 40ft
A - Tape 9.5hr (109-114ft) - MC #12 40ft
A - Tape 10.0hr (115-120ft) - MC #12 40ft

Recessed

  • recessed downlight
  • recessed linear
  • wall grazer
  • troffer
Wiring Method Assembly Path
NM Cable NM ASSEMBLIES/HI HAT - ...
MC Cable MC ASSEMBLIES/HI HAT - ...

For crowded puck light areas: measure length between fixtures, round up to the nearest 5ft

Note

"HI HAT" refers to a recessed can fixture.

Undercabinet Fixtures

Wiring Method Assembly Path
NM Cable NM ASSEMBLIES/UNDER CABINET - ...
MC Cable MC ASSEMBLIES/UNDER CABINET - ...

Note

Takeoff 2 fixtures if jumping over oven

Use 10ft #12/2 for MC & NM

Paddle Fans

Wiring Method Assembly Path
NM Cable NM ASSEMBLIES/RND BOX BAR HNGR...
MC Cable MC ASSEMBLIES/FAN RATED OCT BOX W/ BAR HNGR - ...
PVC PVC/ENT ASSEMBLIES/... - SLAB BOX / 45 DEG STUBBY

Stairwells & Elevators

PVC/ENT ASSEMBLIES/... - SLAB BOX / 45 DEG STUBBY

Facade

Phase = "Facade"

Length and Labor will be more than a normal fixture in BOH/Amenity

Fixture Type Labor (hrs)
Non-Linear 2
Linear See above
  1. 3/4" PVC W/ 3#10 - STL BOX & TILE RING / 45 DEG STUBBY/ ENT DROP
  • Length per Unit = Distance to panel

Porte Cochere (Drive up Area)

Create its own breakout in WBS, and phase in Accubid

This is not technically exposed or drop ceiling, but still use PVC

FAA Lighting

  1. FIXTURE LABOR/FIXTURE LABOR 1HR
  2. FESTOON & ROOF ASSEMBLIES/Aircraft Warning, 3/4" Conduit GRC/PVC 2#10, 1#10G

Controls

Lorem ipsum

Site & Courtyard

Breakdowns

System = "FML - Site Fixtures Material & Labor"

Fixture Assemblies

Fixture Type Assembly Path
Step Light COURTYARDS & LANDSCAPE/STEP FIX, 3/4" CONDUIT - PVC40 - ...
Bollard COURTYARDS & LANDSCAPE/BOLLARD, 3/4" CONDUIT - PVC40 - ...1
Up-light COURTYARDS & LANDSCAPE/PERMA POST, 3/4" CONDUIT - PVC40 - ...
In-grade up-light COURTYARDS & LANDSCAPE/3/4" CONDUIT - PVC40, IMC Elbow, ...
Fixtures built into cabanas/pergolas COURTYARDS & LANDSCAPE/ALUM BOX W/ FLEX FIX, 3/4" CONDUIT - PVC40 - ...
Handrail light COURTYARDS & LANDSCAPE/ALUM BOX W/ FLEX FIX, 3/4" CONDUIT - PVC40 - ...2

Festoon Lighting

AKA "string" or "market" lights

  1. FIXTURE LABOR/FIXTURE LABOR 2HR
  2. FESTOON & ROOF ASSEMBLIES/FESTOON CABLE HANGER & EYE BOLTS - LENGTH
  • Length per Unit = Light string length
  1. COURTYARDS & LANDSCAPE/ALUM BOX W/ FLEX FIX, 3/4" CONDUIT - PVC40 - ...
  • Length per Unit = Distance to panel + 15ft

  1. Determine exact labor from fixture and size. ↩︎

  2. See fixture types below for special cases. ↩︎