Files
zmVault/fixture-designations.md
T

8.5 KiB

id, aliases, tags, title
id aliases tags title
authorship/original
destiny/permanent
occupational/takeoff/fixtures
status/draft
type/guide
Fixture Designations

Fixture Designations

This note details creation of fixture designations for use in fixtures-takeoff.

Naming

Format

<phase-abbr> - <assembly>(\: <subtype>)?( - <fixture-labor>)? \(<wiring-method>\)( <wm-descriptor>)* <branch-length>ft

[!example] A - Surface: Pendant - 2.0hrs (MC) LV 20ft

Order

Use empty designations to separate phases.

[!example]

*** Hotel Units ***
HU - Surface = 1.0hrs - #12 MC+LV 20ft
HU - Surface = 1.5hrs - #12 MC+LV 20ft
HU - Surface: Pendant = 2.0hrs - #12 MC+LV 20ft
HU - Surface: J-Box For Future Fixture = 1.0hrs - #12 MC+LV 20ft
HU - Recessed = 1.0hrs - #12 MC+LV 20ft
*** Condo Units ***
CU - Surface: Tape = 1.0hrs - #12 MC+LV 25ft
CU - Surface: Wall = 1.0hrs - #12 MC+LV 25ft

Fixture Labor

Fixture Type Labor
Paddle Fan 1.5 hr/ea.
Pendant 1-4 hr/ea.
Strip/Cove 0.5 hr/6ft
Site Poles 1.5 hr/ea.
Festoon 2.0 hr/ea.
All Others 1.0 hr/ea.

Fixture Branch Length

Case Standard Length
Site/Courtyard 50ft
Garage 50ft
BOH 40ft
Corridors 40ft
Interior Amenity 40ft
Office/Retail 50ft
Exterior Amenity 50ft
Units 20ft
Undercabinet Fixtures 10ft
Stairwells ?
Kitchen ?

Reduce as appropriate.

Fixture Branch Wire size

Case Wire Size
Site/Courtyard #10
Garage #10
NM Cable #141
All Others #12

Garage

Fixtures

Use ENT assemblies unless forbidden by spec.

FIXTURE ACCESSORIES/PVC/ENT ASSEMBLIES/GARAGE FIXTURE ENT W/#10 - STEEL OCT RING

FIXTURE ACCESSORIES/PVC/ENT ASSEMBLIES/GARAGE FIXTURE W/T ROD ENT W/#10 - STEEL OCT RING

Use threaded rod assemblies in I-beam/precast garages.

If PVC is required, use following assemblies:

Case Assembly Path
Ceiling FIXTURE ACCESSORIES/PVC/ENT ASSEMBLIES/... - SLAB BOX / 45 DEG STUBBY
Wall FIXTURE ACCESSORIES/PVC/ENT ASSEMBLIES/... - STL BOX & TILE RING / 45 DEG STUBBY/ ENT DROP

Homeruns

  • System = "EL - Electrical"

Use 1 Homerun for every 3 circuits in Garage

Use assembly COMMON ASSEMBLIES/Device Homeruns in Slab/Deck

Surface Mount

[!info] Surface Mount Fixtures

  • Wall Mount (Sconce)
  • Pendant
  • Linear
  • Tape
  • Track
Wiring Method Assembly Path
NM Cable NM ASSEMBLIES/RND BOX BAR HNGR...
MC Cable MC ASSEMBLIES/SQ BOX, ROUND P RING & MNTG BRKT...
PVC in Ceiling PVC/ENT ASSEMBLIES/... - SLAB BOX / 45 DEG STUBBY
PVC in Wall PVC/ENT ASSEMBLIES/3/4" PVC W/ 3#12 - STL BOX/TILE RING
EMT EMT ASSEMBLIES/... - SQ BOX & ROUND P RING

Note

Use lighting control cable assemblies in Amenity areas

Tape Lighting

Also called "cove" or "strip" lighting, however those terms are less specific and potentially confusing.

Use item FIXTURE LABOR 1/2HR and change Fct 1 to match the calculated labor (1 hour per 12 feet).

Note

Tape lighting length is limited by the "max power length" of the model (usually measured in millimeters). Max power length is usually 5000-15000mm (~16-49ft) depending on luminous output and voltage.

A reasonable heuristics is

  • 12V strips: 5m (16.4ft)
  • 24V strips: 10m (32.8ft)

Separate these fixtures by labor, not length

*** Back of House ***
B - Surface: Tape = 0.5hr (01-06ft) - MC #12 40ft
B - Surface: Tape = 1.0hr (07-12ft) - MC #12 40ft
_
*** Interior Amenity ***
IA - Surface: Tape = 0.5hr (01-06ft) - MC+LV #12 40ft
IA - Surface: Tape = 1.0hr (07-12ft) - MC+LV #12 40ft
IA - Surface: Tape = 1.5hr (13-18ft) - MC+LV #12 40ft
IA - Surface: Tape = 2.0hr (19-24ft) - MC+LV #12 40ft
IA - Surface: Tape = 2.5hr (25-30ft) - MC+LV #12 40ft
IA - Surface: Tape = 3.0hr (31-36ft) - MC+LV #12 40ft
IA - Surface: Tape = 3.5hr (37-42ft) - MC+LV #12 40ft
IA - Surface: Tape = 4.0hr (43-48ft) - MC+LV #12 40ft
IA - Surface: Tape = 4.5hr (49-54ft) - MC+LV #12 40ft

Recessed

[!info] Recessed Fixtures

  • recessed downlight
  • recessed linear
  • wall grazer
  • troffer
Wiring Method Assembly Path
NM Cable NM ASSEMBLIES/HI HAT - ...
MC Cable MC ASSEMBLIES/HI HAT - ...

For crowded puck light areas: measure length between fixtures, round up to the nearest 5ft

Note

"HI HAT" refers to a recessed can fixture.

Undercabinet Fixtures

Wiring Method Assembly Path
NM Cable NM ASSEMBLIES/UNDER CABINET - ...
MC Cable MC ASSEMBLIES/UNDER CABINET - ...

Note

Takeoff 2 fixtures if jumping over oven

Paddle Fans

Wiring Method Assembly Path
NM Cable NM ASSEMBLIES/RND BOX BAR HNGR...
MC Cable MC ASSEMBLIES/FAN RATED OCT BOX W/ BAR HNGR - ...
PVC PVC/ENT ASSEMBLIES/... - SLAB BOX / 45 DEG STUBBY

Stairwells & Elevators

PVC/ENT ASSEMBLIES/... - SLAB BOX / 45 DEG STUBBY

Facade

  • Phase = "Facade"

Length and Labor will be more than a normal fixture in BOH/Amenity

Fixture Type Labor (hrs)
Non-Linear 2
Linear [See tape lighting](#Tape Lighting)
  1. 3/4" PVC W/ 3#10 - STL BOX & TILE RING / 45 DEG STUBBY/ ENT DROP
    • Length per Unit = Distance to panel

Porte Cochere (Drive up Area)

Create its own breakout in WBS, and phase in Accubid

[!quote] This is not technically exposed or drop ceiling, but still use PVC

Site & Courtyard

Important

Coordinate with landscape

Breakdowns

  • System = "FML - Site Fixtures Material & Labor"

Pole Lights

FIXTURE ACCESSORIES/SITE POLE ASSEMBLIES/...

Add subassemblies for stub-outs, pole, base, and grounding as appropriate.

Festoon Lighting

[!info] Also Known As

  • string lighting
  • market lighting
  • catenary lighting
  1. FIXTURE LABOR/FIXTURE LABOR 2HR
  2. FESTOON & ROOF ASSEMBLIES/FESTOON CABLE HANGER & EYE BOLTS - LENGTH
    • Length per Unit = Light string length
  3. COURTYARDS & LANDSCAPE/ALUM BOX W/ FLEX FIX, 3/4" CONDUIT - PVC40 - ...
    • Length per Unit = Distance to panel + 15ft

Other Fixture Types

Fixture Type Path (FIXTURE ACCESSORIES/COURTYARDS & LANDSCAPE/...)
Step Light .../STEP FIX, 3/4" CONDUIT - PVC40 - ...
Bollard .../BOLLARD, 3/4" CONDUIT - PVC40 - ...2
Up-light .../PERMA POST, 3/4" CONDUIT - PVC40 - ...
In-grade up-light .../3/4" CONDUIT - PVC40, IMC Elbow, ...
Fixtures built into cabanas/pergolas .../ALUM BOX W/ FLEX FIX, 3/4" CONDUIT - PVC40 - ...
Handrail light .../ALUM BOX W/ FLEX FIX, 3/4" CONDUIT - PVC40, IMC ELBOW - ...

FAA Lighting

  1. FIXTURE LABOR/FIXTURE LABOR 1HR
  2. FESTOON & ROOF ASSEMBLIES/Aircraft Warning, 3/4" Conduit GRC/PVC 2#10, 1#10G

  1. Minimum #12 in kitchens and bathrooms. ↩︎

  2. If we don't own concrete, delete Pre-cast bollard base from assembly ↩︎