# Fire Alarm
|
|
|
|
## Sequence
|
|
|
|
### 1. Estimate preparation
|
|
|
|
1. Initial the OneNote
|
|
2. Read about the project specifications and construction type
|
|
3. Find Fire Alarm plans (if present)
|
|
4. Locate the following rooms:
|
|
* Fire Command Center (FCC)
|
|
* Generator Room
|
|
* Fire Pump Room
|
|
* Elevator Control Rooms
|
|
* Elevator Shafts
|
|
* Stairwells
|
|
|
|
### 2. Takeoff
|
|
|
|
#### Riser
|
|
|
|
##### Fire Command Center
|
|
|
|
{Building Type} Head End CA.30.23.X
|
|
|
|
##### Generator Room
|
|
|
|
CA.30.22.2
|
|
|
|
##### Fire Pump Room
|
|
|
|
CA.30.22.4
|
|
|
|
##### FACR to Elevator Shafts
|
|
|
|
Elevator Shafts (CA.30.22.8)
|
|
|
|
FACR TO ELEV SHAFT 1 ½" (CA.30.22.10/11)
|
|
|
|
Measure Length from the most distant points of the FACR and each shaft.
|
|
Input adder length to reach the bottom of the pit
|
|
(Minimum 15ft adder).
|
|
|
|
```
|
|
| 1 shaft | 2 shafts |
|
|
| || +--------+ +--------+ || | || +--------+ || +--------+ || |
|
|
| || | Elev 1 | | Elev 2 | || | || | Elev 1 | || | Elev 2 | || |
|
|
| || +--------+ +--------+ || | || +--------+ || +--------+ || |
|
|
| ||=======================|| | ||============||============|| |
|
|
| | |
|
|
```
|
|
|
|
##### FACR to Elevator Control Rooms
|
|
|
|
Elevator Control Room (CA.30.22.6)
|
|
|
|
FACR/FCC TO ELEV CONTROL ROOM (CA.30.22.13/14)
|
|
|
|
* Measure the Horizontal and Vertical Distance from the FACR to the ECR.
|
|
* Use Typicals for the vertical riser. (Ex// 10' per floor)
|
|
|
|
##### FACR to Stairwells
|
|
|
|
FACR TO STAIRWELLS 1" PVC (CA.30.22.17)
|
|
|
|
* Measure from the furthest end of FACR to the furthest end of the stairwell to find length
|
|
|
|
* This is for the Flow/Tamper modules in the stairwells
|
|
|
|
##### Terminal Cabinets
|
|
|
|
TERMINAL CABINETS (2) 2" EMT/PVC (CA.30.26.X)
|
|
|
|
Horizontal:
|
|
* Measure from the Fire Command room to all electrical rooms
|
|
|
|
Vertical:
|
|
* Use 10ft Riser in Typical
|
|
* GA or HD - 1" conduit / HR - (2) 2" conduits)
|
|
|
|
##### Annunciator Panels
|
|
|
|
* Fire Alarm Annunciator (FAA),
|
|
* Fire Alarm Annunciator Panel (FAAP)
|
|
|
|
ANNUNCIATORS (CA.30.27.2/3)
|
|
|
|
Remote Serial Annunciator, LCD Display - PVC
|
|
|
|
* Measure from the Fire Command Room to FAA or Lobby
|
|
|
|
##### Sleeving
|
|
|
|
#### Devices
|
|
|
|
1. Takeoff floor plans in order
|
|
2. Takeoff enlarged drawings
|
|
|
|
##### Smoke Detectors
|
|
|
|
_Design Build:_
|
|
Count every stairwell at every level.
|
|
|
|
##### Pull Stations
|
|
|
|
_Design Build:_
|
|
Count every stairwell at every level
|
|
and every exterior exit.
|
|
|
|
##### Flow-Tamper Switches
|
|
|
|
No free air. if wood frame, take off as EMT.
|
|
|
|
_Design Build:_
|
|
Count every stairwell at every level.
|
|
|
|
##### Magnetic Door Holders
|
|
|
|
Mech Connection - PVC AL Flex - 20 A
|
|
|
|
_Design Build:_
|
|
Count every set of double doors.
|
|
(Typical of elevator lobbies and corridors)
|
|
|
|
##### Speaker Strobes
|
|
|
|
_Design Build:_
|
|
* Count every 75 ft,
|
|
* measure with circles on Bluebeam
|
|
* or divide relevant SF area by 4415
|
|
* $\pi(\frac{75}{2})^2 \approx 4415$
|
|
* every elevator lobby,
|
|
* and every BOH room on the first floor and garage levels.
|
|
|
|
#### Fire Smoke Dampers (FSD's)
|
|
|
|
Take off both FA and Electrical
|
|
* Misc Assemblies
|
|
|
|
### 3. Extension (Review and Checking)
|
|
|
|
* Sleeving
|