Switchgear
Sequence
1. Estimate preparation
- Initial the OneNote
- In the drawings, locate:
- Riser Diagrams
- House Panels
- Copy over default Temporary Assemblies from sandbox job
2. Takeoff
-
Build Items in Distribution:
- Panelboards
- Switchboards
- Meter centers
- Generators
- Transfer switches
- Generator connection cabinets
-
Takeoff Common Assemblies:
- XFMRs
- Disconnect switches
-
Takeoff Items in Item Database:
- Wireway (Trough/Gutter)
-
Takeoff Temp Assemblies:
- CT Cabinet
- Meter
- Fire Pump
- Fire Pump Controller
When building panelboards/switchboards, add terminations according to an example from the schedules. Do not include feeder terminations.
Items to Avoid:
- Tap Boxes
- Bus Duct
- Vault Room
- Anything FPL
- Grounding
- Elevator Room
SPD's/TVSS's
Labor only: ~1.5hrs
Panelboards
DISTRIBUTION/DIST PANELS & UNIT LOAD CENTERS/...
Enclosed Circuit Breakers
Treat as disconnect switch.
Generators
Add GENERATOR SET UP
Generator Connection Cabinets
Use a Distribution Panel of equal amps.
Transfer Switches
"300A ATS"
Transfer Switches 1200A+
Use 1200A MTS/ATS, and add:
- ==CA.33.14.AMPS==
- Factor 1 = 3
- ==Delete 1200A==
Meter Centers
SWITCHGEAR & METER CENTERS/METER CENTERS/... METERING SECTION
Adjust Factor 1 for meter stacks, delete zeroed items.
3. Extension (Review and Checking)
- Generator
- Ensure takeoff is in the generator Area and System breakdowns
- Put location, quantity, and type on OneNote