2100 Crystal Drive Closeout
Notes on 2100-crystal-drive as reviewed with joel-jansen:
Extension
#600 ? WHITE ? had incorrect sort codes.
Lighting Control
Relevant to lighting-controls-takeoff:
I took off lighting per plans (E510) in spite of proposal stating "local control". Will have to be changed.
Labor Factor
Fire Alarm Switchgear Feeders Subfeeds Corridors Amenity Retail Units
Fixtures
Relevant to fixtures-takeoff:
[!failure] Several fixtures were erroneously based on NM cable.
I built some fixtures with #12/3 in areas with emergency lighting to be an unswitched hot. Joel is having me change them to #12/2.
Units
[!failure] One unit type typical was missing
Areaquantities. Another had no takeoff.
Labor Plan
Relevant to pdi-labor-plan:
\mathbb{E}\left[\frac{\text{Hours Per Unit}}{\text{Openings Per Unit}}\right] \approx .75~\text{Hours Per Opening}
High-Rise .110--.120 hr/sqft