title: Project Start Notification
|
|
tags:
|
|
- authorship/other-for-now
|
|
- occupational
|
|
- type/guide
|
|
---
|
|
# Project Start Notification
|
|
|
|
Save all documents below to ".\8. PSN Docs"
|
|
|
|
## Feeder Verification
|
|
|
|
For `System` = "FRR - Feeders and Risers", "PRI - Primaries", and "SEC - Secondaries"
|
|
|
|
1. Filter Takeoff by `System`
|
|
2. Copy and paste all lines to Excel
|
|
3. Remove all columns except _Description_, _Length_, and _Count_
|
|
4. Make a note of any typicals
|
|
5. Repeat process for systems
|
|
|
|
Save to ".\8. PSN Docs\ {Job} - Feeder Verification.xlsx"
|
|
|
|
## WBS
|
|
|
|
"S:\Estimating\19 WBS Agreement GP\4. Award Agreement WBS\ ..."
|
|
|
|
Export Awarded WBS to PDF, or just copy if available.
|
|
|
|
## Procurement Accubid Export
|
|
|
|
In master Accubid file,
|
|
group by `System`, `PDI SORT CODES`.
|
|
|
|
Export ==**Extension** only== as ==**Excel**==
|
|
to ".\8. PSN Docs\ Procurement Export - {Job}.xlsx"
|
|
|
|
## CBOM
|
|
|
|
### CBOM Accubid Export
|
|
|
|
In master Accubid file,
|
|
group by `Bid Item`, `System`, `PDI SORT CODES`, `Area`, `Phase`.
|
|
|
|
Export ==**all tabs**== as ==**csv**==
|
|
to ".\6. Notes & Emails\Accubid CBOM - {Job}"
|
|
|
|
### Import
|
|
|
|
Open Award Agreement WBS:
|
|
"S:\Estimating\19 WBS Agreement GP\4. Award Agreement WBS\2026\Electrical\WBS - {Job} {Date} EVP Approved.xlsm"
|
|
|
|
`WBS Import/Export > BOM > BOM Export`
|
|
|
|
`Delete File` until only one remains,
|
|
in that item, click $\vdots$ and select the export csv.
|
|
|
|
It will error the first time. Try again.
|
|
|
|
Do not save the WBS.
|
|
|
|
Delete labor-only tabs:
|
|
* "Lighting"
|
|
* "SwitchGear"
|
|
* "Generator"
|
|
|
|
## Labor Plan
|
|
|
|
Copy ConEst Labor Plan
|
|
|
|
".\1. Labor Plan & Estimate\ConEst Labor Plan ..."
|
|
|
|
## Unit Matrix
|
|
|
|
Save as Excel with only unit matrix.
|
|
Remove area breakouts, etc.
|
|
|
|
## Distribution List
|
|
|
|
After bell is rung, attach all docs and send to stakeholders.
|
|
|
|
* To: PM, PX, RVP, SVP, Super
|
|
* CC: Commodities Buyer, Procurement PX, ITR Team, PCO Team, ConEst Manager, Jessalyn Williams
|
|
|
|
Reach out to Chief's Coordinator for PSN Summary Chart to get list of PM's & PX's
|
|
|
|
See "S:\Estimating\7 ConEst Team\ConEst Process Documents\PSN Documents Distribution List.xlsx"
|
|
for others.
|