title: Distributed Antenna Systems (DAS) Takeoff
---
# Distributed Antenna Systems (DAS) Takeoff
> [!important]
> Complete [[emergency-systems-research]] before beginning takeoff.
> [!info]
> See [[emergency-communications-systems]] for information
> about Emergency Responder Radio Communication Systems (ERRCS).
> [!info] Cellular Systems
> Less common than ERRCS are "cellular DAS" systems
## Backbone
### FACR to Every Elevator Shaft
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`FACR TO ELEV PIT = ...`
Match Fire Alarm takeoff Length and Count
### FACR to Every Staircase
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`FACR TO STAIRWELL = ...`
Match Fire Alarm takeoff Length and Count
### Stairwell Riser Every 2 Floors
> [!info] Takeoff
> * `Area` = "Typical - Stairwells Building Even Levels"
>
> 1. `COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`STAIRWELL RISER EVERY 2 FLRS = ...`
> * **Count** = Each stairwell
### FACR to Electric Room
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`FACR TO 2HR-RATED RM = ...`
Match Fire Alarm takeoff Length
### Electric Room Riser to Every Floor
`COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`2HR-RATED RM RISER TO EVERY FLR = ...`
Takeoff in every Electric Room
### Top 2H Rated Room To Roof
> [!info] Takeoff
> 1. `COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`TOP 2HR RATED RM TO ROOF = ...`
> * **Length** = 15ft or height of ceiling on last building level
## Horizontal
> [!important]
> Usually only for cellular DAS.
> Confirm takeoff requirement with [[pdi-estimating#Bid Estimating|Bid]].
> [!info] Takeoff
> 1. `COMMON ASSEMBLIES`/`FIRE ALARM & DAS SYSTEMS`/`DAS ASSEMBLIES`/`CORRIDORS ...`
> * **Length** = Length measured for every corridor/garage